Wednesday 26 June 2024

Steels go up.

Thursday at Broadway on P2.

We are gearing up to lift in the second pair of ring beams, and start the plinth of blue engineering bricks.

It should happen some time next week.

First of all we have to move the steels under their intended positions. This wasn't too difficult, with two men moving them easily by means of a little piano truck

Here they are in place. You may also notice two little ramps, ready for the Genie lift that we are renting.

 

 

 

Neal then got the angle grinder out, and ground some little tear drops of steel off the ends.

This issue became apparent with the first two beams. Once you are up on the ladder trying to bolt them down, you don't want to find out that there are a couple of mm of steel holding them apart. 



 

 

 

 

 

And here are the beams in place, ready for lifting next week .

The platform covered in thick plywood will support the genie lift. We will also use it to fix the temporary cross members (those rusty red things in the background, salvaged from the P1 build.)

 

 

Back to the build. The station was quite busy on Thursday, less so with this diesel hauled train, more so with the other, hauled by 2807.



When the train had left and things were quieter, we decided to treat ourselves to a cuppa and an ice cream.


This is the life !

Back on P2, we stepped aside to let the steamer run round, giving rise to this lovely cameo of Neal watching 2807.

The loco was driven by a former Honeybourne fireman!


Having positioned the steel beams, we spent the rest of the day positioning piles of blue engineering bricks around the perimeter of the building, ready for the construction of the blue plinth to start. We are using new blue imperials. They are very heavy, and wore out one builder's glove of Yours Truly. Neal reports that they weigh 3.7Kg each, and that instead of 500 metrics per pallet as in the CRC P2 rebuild, there are only 380 in a pallet with these bigger imperials. And that pallets weighs in at a tonne and a half. We spread out one pallet, so that is 1 1/2 tons that we manhandled on Thursday.

The concrete blocks are for the internal walls of the store room.
 

For those interested, here is a link to the camera on the footbridge, operated by the FoBS:

https://www.ipcamlive.com/broadway2a 

If you make yourself a bookmark, you can go there directly any time you want. It's also been added to the list of links on the top right of the blog.

 

PWay on Saturday.

Pictures by Paul, with one team at Gotherington, and a second at CRC, with fishplate greasing also taking place, and possibly completed for this year. So a good day.




The Gotherington team (with Paul) changed 3 sleepers at the platform end.

Here they are being dug out.

Two problems here: The sleepers in question had spikes for rail fastenings, a rarity (luckily) on our line. They work loose, but are hard to remove. They need to be cut.




 

 

The second problem was the location: right by a central drain cover. One spiked sleeper was hard up against this drain, so could not be removed in the normal way. In the end three sleepers were replaced here, to gain some space.



 

 

The spiked sleepers at Gotherington were replaced by Pandrol fitted ones on base plates.

After much digging these were wriggled in and pushed to the right spot, by the drain cover.




Paul also took this rather nice picture of newly overhauled 2807, arriving by platform 2.

The owners of Gotherington make a fine job of keeping their station neat and tidy, and looking real. If only BR hadn't cut back the canopy ends. They now mark the actual property line.

The other two teams were at CRC, where some dips were ironed out and fishplates greased. They then all joined up in the Coffepot at Winchcombe, the best place to be.



Sunday was a day on the cushions for us, with some visitors from Hilversum.

We were going to take the 11.15 to CRC, but held back when we saw what was hauling it.

Instead we preferred the 11.40 steamer to Broadway, then a round trip.

The visitors declined an offer of free (shareholder's ) tickets, and felt they ought to pay, to give the railway some cash. What nice people they were...



Monday at Broadway on P2.

A long awaited day, and not only by our readers. On Monday we lifted in the second pair of ring beams, and made a start on brick laying on the P2 building. A great day !

 

 

 

This is the opening shot, from the footbridge. The ring is partially complete, with the remaining two steels on the ground. Three bracing strips are also just about visible on the floor. They were salvaged from the P1 build.

 

 

 

 

The two beams lifted in quite easily, and here you see Neal bolting on the bracing strip.

This will come off again in due course, and be replaced by a truss, which does the same job.

 

 

 

 

The last angled bracing piece was placed on the end, helped by a Genie lift.

Our building now has a shape and volume, which gives you a better idea of what it can be used for.

It occurred to us that a bar in here, during the beer event, would be perfect.

All the uprights were perfectly straight, and we had no trouble in bolting all the different pieces together. Another fine job by Neal !

 

The steels took less than a morning, and that gave us the opportunity of making a start on the brick laying. There will be 5 courses of blues to form a plinth, so that is what is being laid at the  moment.






We couldn't resist a record shot of the first brick of the P2 waiting room at Broadway going on.

These are 3.7Kg imperial blues, the real McCoy.

Occasionally one needs trimming, so this is what Neal is doing here.

Yours Truly made the mortar, which was dyed dark grey, to simulate the ash that used to be put in.



 

 

Recently John also went to fetch the last 6 Broadway lamp tops, from a  Coppersmith who does an excellent job.

They now need painting, and we prefer to replace the plain steel nuts & bolts with SS ones, so that will be a shed at home job.




 

At the end of the day John had laid a good 40 bricks.


This picture was taken mid-afternoon, after which he laid some more. He made it to the S end of the building, and a bit beyond the gap for the door in the foreground.




Wednesday with a full complement of Usketeers.


At last, John (replacement car bought) and Dave (back from Devon) brought the little team back up to its current strength of four.



 

We had three jobs on the go - two hole diggers, a gate hanger, and a creosote operative. The latter job has to be done at least a week in advance, as it can't be done in the rain, and you don't know what next week will bring.

In the picture Paul is fitting the lower hinge to the small gate, the post we placed last week now having gone off.




From the double gates we can go in two directions:

Dave here is going north, and is busy digging the first post hole of the fence that leads away from the gate. We have a curve to deal with here, as well as some undergound cabling to avoid.





 

On the other side of the gate we had John, who was digging the first post hole south of the gate.

As you can see from the faces, there is a problem. After about a foot John hit a large root. Now what?





Paul attached the lower hinge to the smaller gate (it's the top hinge that does all the load bearing, we learned)


And after some adjustment the smaller, pedestrian gate was in. This will allow passengers arriving by coach to get to the station directly from the triangular coach park.

There will be a drop bolt underneath, which will permit the small gate to be opened independently.




Wednesday was a hot day (27 degrees C) and the Usketeers escaped to under the trees for coffee and cake.

Yours truly went to the Cotswolds Halt, where this Orange Cake looked attractive. It was both Gluten and Vegan free.

Whatever - what matters to us was the taste! Give it a try, why not.

Afterwards the Usketeers relaxed among the lime trees. Relaxed, until they relaised what lime trees did to their cars, also underneath. Oh-oh !





Working in parallel with the Usketeers was a team from C&M, who were repairing a much older section of featherboard fence by the sliding gate.

We like to take a picture with people on it, but there were none !




 

 

 

We'll have to add the people separately - here they are, enjoying a coffee break in the shade.


Smile !

 

 

 

 

Over on P2 at Toddington we found one of the posters commissioned by the RATs, which this blog has helped to source.

 

We are currently organising three more, of which two for Broadway, P2, of the turn of the century era.

You'll have to wait and see, all part of the planning.


In between times we saw 7903 Foremarke Hall running into Toddington.


Then it was back to the job at hand, i.e. erecting the gates and the surrounding posts for the start of the post and rail fencing.

Here Paul is drilling the first holes for the fence post, on a grandfather post, next to the gate.



 

John and Dave had dug three post holes. They are always an adventure, as you never know what is down there.

Here Paul and Dave a loading up some postcrete for the first grandfather post.





Then here is where it went.

The first grandfather post southwards is already in, and in the picture you can see them about to shovel in Postcrete down the hole for the post by the fence.

The post nearest the camera was a difficult one, as John hit a big tree root here. We had to move the intended route by a few inches.



 

 

 

 

After two posts were set south of the gate, the three of them addressed the first grandfather post northwards.





 

Three grandfather posts set for the day, and two of them with wooden posts attached, was about it for the day.


Yours truly spent most of the day preparing further woodwork for use, making hay while the sun shone. The sunshine dried out the pallets of posts that we had delivered. All were pretty wet inside, despite hot weather and tarpaulins thrown over the top.

We laid future woodwork out on the ground, and the firece sunshine soon dried it out. Then it was creosoted, ready for next week. If it rains then, we are still ready to go.

This is our last shot of the new fencing run for the day.

Both gates are now hung, and concrete posts are set on both sides, ready for rails next week. We are off to a flying start.




PWay on a hot Wednesday.

 Pictures by Paul and Walt, with thanks.

 

 

 

The job for the day was to investigate the overgrown yard at Stanton, and see if there wasn't a switch buried in the undergrowth.

 

 

 

 

 

 

 

 

The answer seemed to be 'Yes' but what did it look like?

The PWay team is not equipped to deal with a lot of undergrowth, so it was basically hand weeding, something which is anathema to Your Blogger, who suffers from hayfever and related asthma. (if provoked)

We stayed safely under the shadow of the lime tree by the new gates at Toddington, but impressed by the team members that could attack the undergrowth..







Piles of military grade sleepers peeped out of the brambles.

These could come in handy for a relay of sidings that we have pencilled in for a future job.









 

It was amazing to what depths the team members could penetrate the undergrowth.

Many of us wondered - what are they doing in there? Some suggestions made by unkind observers were hotly denied.


But the reward for a day's hacking was one FB switch, fully exposed.

The switch was pulled out by the Telehandler, for further examination.




11 comments:

  1. Excellent progress on al fronts. May the weather gods shine on your brick laying efforts for months to come!

    ReplyDelete
  2. On replacing the nuts and bolts in the copper lamp tops, you need to be careful as copper and stainless steel don't play well together, you can get corrosion in the copper, possibly why the maker used plain steel ones.
    regards
    Rodger

    ReplyDelete
    Replies
    1. Thanks, so that's going to be tricky.
      Leave the mild steel bolts, and they go rusty. Change to Stainless Steel, and the copper suffers.
      I'll see if we can fit some sort of fibre washers.
      The 10mm bolts will be OK, as they hold the frog on to the cast iron posts, and they go into steel.

      Delete
    2. Brass bolts may work, Neil.

      Delete
    3. Are copper nuts and bolts available?

      Delete
    4. We already have the SS nuts and blts, and have ordered nylon washers to separate SS from copper.

      Delete
  3. Sorry I missed you all at the.coffeepot , having done the last Spy turn for the summer term with Winchcombe school who have not been since before COVID .

    I recall Stanton yard having several switches stacked on LHS belonging to Andrew Goodman which he may still want for Sharpness but that seems to be going nowhere .

    2807 crew very pleased with track ride and that’s thanks to you all . Good to see Doug W in the thick of things again , Daily M !

    ReplyDelete
  4. Excellent progress on the ring of steel at Broadway. I was hoping to watch the action live via the Broadway cam, but ,alas, it was switched off. I didn't realise that you had started the brickwork. Well done!
    Would be nice to work in the shade, but you have to build the building to get the shade!!
    And once you have the shade from the building, you don't really need it then. Catch 22.
    Regards, Paul.

    ReplyDelete
  5. Will the English bond style of brickwork be adopted in the Platform two build?
    Regards
    Richard T

    ReplyDelete
    Replies
    1. Richard The brickwork will be the same as with the platform one building, the blue brick plinth is a double course of bricks stepping back to a single course when the red bricks start. To comply with modern regs the build has a cavity wall. The headers will be cut in half to give the correct appearance on the face. The steel frame supports the roof structure, were the original buildings had solid walls.
      Neal

      Delete
    2. Thanks, that will mean a lot of extra work and angle grinder discs, but good to know it will retain the appearance of the original building. I remember seeing photos of the brick cutting in the old platform 1 blogs. (Including a lot of red dust!)

      Richard T

      Delete