Canopy lift completed.
Monday was the big day, a non-running day of course. We had hired an 80 tonne crane in, and our train of loaded canopy parts was due in from Toddington. That train was delayed by an hour - while it was loaded and ready to go on the Parlour Road, both platforms at Toddington were full of carriages, so a big shunt had to be carried out first.
The Elliots crane was already there at 8 o'clock, ready to deploy.
They had a slinger with a Walkie-Talkie on the train, and a driver on board the crane listening for instructions. A bit old fashioned, but it worked perfectly.
Before we start, here's a quick overview of the P2 building without any steels on it. Check it out with the pictures at the end of the blog post....
We waited eagerly for the 03 and its station canopy kit to arrive. Finally it trundled in.
The train ran straight into platform 2, from where it was unloaded, piece by piece, by the crane situated out of sight on the forecourt.
First came the woodwork. This was stationed on top, in such a way that its height did not interfere with the trusses that would reach across.
Then came the first truss. Neal had loaded the MACAW in such a way that unloading was very logical for the slinger. Neal had clearly thought this through, and so it proved for the rest of the day too. Everything went well.
We had quite a little crowd, not only from among the volunteers, but some of the neighbours came to look as well.
The jib of the crane was so tall that it was impossible to photograph the whole thing, except perhaps from the south end barrow crossing, which would have made everything look tiny in the distance.
Remember that the top of this jib was hovering over the middle of the new building, way out of sight.
Here is the second truss going in. This first one went on the three canopy support posts, and was securely bolted down. Much hole drilling still faces Neal, then all the bolts can be fitted, and then they will have to be removed again, to be replaced by proper rivets.
The positioning of the second truss makes it possible to try a ridge purlin in between.
Would the distances work?
Here comes the first of the three ridge purlins.
Would it fit in between?
It did fit - phew! Neal had not made any mistakes with his measurements.
Now for the next truss.
Then the second ridge purlin, right in the middle. That too connected with the two trusses without any problems.
A shot down and along the canopy, with the second ridge just being dropped in.
Finally the fourth truss was lifted on, with the last of the three ridges left on the MACAW.
It was all so simple, and well thought through!
Then it was the turn of the fascia boards, three along the front and one on the back, behind the canopy overhang.
It has to be pointed out that we were unable to secure use of the run round loop for the scaffolding needed to fit the fascia boards, and items that need to be attached to them (dagger boards, timbers, guttering, and painting of all those). We attempted a track possession over the winter, but that proved not to be possible as there were commercial requirements overuling us. So we decided to move the lift to the summer, when there is better weather, and do what we can with a smaller amount of scaffolding.
The central fascia board was fitted first. Two volunteers worked from ladders to put in the necessary bolts to secure them.
An overview of the partly assembled canopy, and the 80T crane standing on the forecourt. The end of the jib was too high to fit the picture, even when stood well back.
The second fascia board was fitted on the south end, and bolted to the middle one (as well as to the end of the truss).
Then it was the turn of the third one, of the set of four.
The fourth one goes on the rear end of the canopy overhang
Here the crane is holding it against the ends of the trusses, as Neal and Ian try to get some bolts in. On Neal's assurance that the heavy board is secure, the chains are released and the slinger gives the next signal to the crane driver.
A close up of Neal and Ian trying to get the bolts in.
It was amazing how everything fitted so well.
Now the chains can be released.
As we went to get something from the car, we turned round to see the extent of the huge crane, and its fully extended jib.
Here the crew are making a start on the purlins themselves. These run lengthways along the middle of the two arms of the trusses.
In the foreground is the fourth fascia board. This is the only item not fitted on Monday, although it was laid on a pair of trestles close to where it will go.
The far end needs to cut into the brickwork, and cutting that could not be done on the day.
A bit hard to see, but here another purlin is being lifted in.
We are looking down the ridge of the canopy, which is both platform canopy and station roof.
Fitting the second purlin over the site of the canopy overhang, a large area at the foot of the stairs which will be glazed, and carry a large replica gas lamp, that was sponsored by a blog reader.
The final items that were fitted were latticework supports for the roof sheets.
The one in the foreground is paused, pending rearrangement of the stockpile of timbers in the central section.
All steel items were successfully installed on Monday, a big feather in the cap of Neal, who built the entire structure in pieces so accurately, that everything fitted together on the day without the slightest problem.
This picture shows how the fascia board overhangs the platform edge, and why, ideally, we would have liked to extend the scaffolding into the 4 foot, as was done during the construction of the P1 building.
Tuesday at Broadway.
The first day after the big lift. It was the start of a long list of smaller jobs on site. Neal was drilling holes, John was laying bricks along the back, and Yours Truly cleaned, derusted and primered rivet heads that had been left bare and rusty.
Here's an example of a rivet head that was once primered, but had no protective undercoat applied. The primer does not protect against rust, so after a while the rust develops underneath, and comes through.
This is what it would look like, if undercoated right from the start.
And this picture shows the process - cleaning of the rivet heads with a rotary brush, then the application of Kurrust, as in the picture.
Later in the day we applied primer, and will follow that with undercoat next time. Then the whole lot can receive its top coat.
It was very annoying to be the subject of a power cut on Monday, with only a quick half hour's worth of work possible at the start of the day.
Grrrr - why do we have a power cut??? They seem very common in these parts.
We had noticed that our farmer neighbour had been doing stuff to her field, including the construction of two new houses by the main farm. On Tuesday we observed a man in an orange jacket, with a ladder. He was sitting in the grass, later on, even lying in it! It's all go, down there...
One of the S&T gang, working on preparing Broadway box for actual operation, called out to him, and he said that he was waiting for a phone call. So were we! The wait took two hours. It took a large chunk out of our working day. We couldn't even go for a coffee, as the cafe was on the same circuit.
Neal was working on steels, mostly drilling holes for junction plates, such as this one here.
Here he is drilling holes through a pair of such plates. These are destined for the bottoms of the arched ridge purlins; in fact, just above Neal's mag drill in the picture.
In this picture he is just doing a test fitting, at the opposite end of the same ridge. This plate has 5 holes in it, and there are many such plates, so you can imagine the volume of work required.
At the back we find John laying plain bricks in a row along the back. This row is one of 4 along the corbels here. Before we put the roof sheets on here we would prefer for this brickwork to be finished.
There are two more courses to go along here, after this one.
Trains are still diesel hauled, and not terribly full as a result. This 15.30 train was busier though, mainly with people returning from the village, after shopping there.
We had a chat with our new lady marketing manager. We are not having a brilliant year results wise, due to the landslip shortening services, a steam ban, and even a complete stop on the hottest day this year. We must do more to sell ancillary services, and she took a great interest in the P2 function room that we are building as a result. She is keen for it to start earning money as soon as possible, and sees lots of opportunities for the space, providing that we do not fill it with stuff. For example not long ago we had a request for a venue to hold a wake, and almost had to turn it down.
Wednesday at Broadway.
Overnight rain, but dry on site. We caried on drilling, laying bricks along the back, and painting steel.
Neal spent the day drilling and bolting up junction plates, here at the end of the ridge purlins.
Yours truly has a longish task, after making up the initial load of mortar, and supplying John with bricks, of touching up all the paintwork damage occurred in loading, craneage and assembly. This involves applying Kurrust, then a metal primer, followed by an undercoat. That puts the damaged area back to where the rest is at.
So far we have done about half of the construction. Then the whole thing has to be top coated, after riveting.
It's still a LIME coloured timetable, so today we had two Growlers. Very nice, and seemingly also quite popular, as the platforms became very busy at one point.
We need three more courses of bricks along the back, part of a 4 course corbel, three of which are specials.
John was in excellent form today, and finished the course of plain bricks, and starting the next course of bevelled headers.
Here they are being set out.
On this SW corner you can see all 4 of the corbel courses.
John is currently working on the middle two, with a bull nosed top course still to come.
The crowded platform mid afternoon could be explained by these two coaches - good business for us.
The Growler (the Green Goddess one) is just coupling up.
Wednesday on the Usketeers.
With Yours Truly committed to supporting the canopy gang this week, there were three Usketeers today. They set off for Gotherington, to make a start on the leaning ground frame hut.
The Usketeers quickly made themselves at home in Bryan's garden....
The early morning coffee was held in the usual way - chairs were high in their thoughts before they set off.
But eventually they did have to get to work. The first thought was to open up the foundations and see what was going on down there to make it lean. Bryan thought of Badgers or Rabbits (he has a lot of these); our initial thoughts were more along the lines of wood rot and/or a drainage issue.
The hut was built by Bryan to stand on 4 concrete plinths, with a wooden sub frame on top of them.
The first job therefore was to dig a trench all the way round, to reveal the condition of the structure below ground.






























































