Thursday at Broadway.
A dry day (we thought) so an opportunity to be seized for painting more of the steelwork on the Broadway P2 roof.
No painting pictures though - what could we show? It's repetitive work, not very interesting. It wasn't easy on Thursday though, as it had rained hard overnight and although the sun was shining on arrival, the steelwork was wet all over. Can't paint like that. We removed as much of the water (in the angle iron particularly) as we could with a rag, leaving just a damp film. We then went down to the cafe for a cappucino and a bun, to let the sun do its work.
The result for the day was a whole bay painted, one of three. So we're 2/3 of the way there to giving the whole structure its second undercoat.
There was evidence of work from Wednesday (our usketeering day) as there are now three arches in (out of the 8), and John has been filling in the bricks in between, and above.
Also interesting was this supporting woodwork that Neal has put up. This will support the dagger boards and the guttering in due course. All the fascia boards need this sort of woodwork, so there is still a way to go.
Neal also bolted some of the wooden supports for the roof sheets along the purlins, and here is a large piece of timber at the end.
This is the bottom of the structure for the dagger boards that close off the roof from the end.
Friday gang at Toddington.
Four of us on 'operation clean up the greenhouse yard' at Toddington.
This is the size of the problem (picture by Paul).
It's true, a lot of the piles of material there are from the PWay. A gang of 4 met with two vans and two Telehandlers to take it away, or as much as we could in a day. Actually, it's at least the third day of taking it away. But it's working! There is a lot less already.
The first job was to remove the stacks of heavy rubber pads for crossings, and take them to Stanton yard.
Both Transits were used, in a shuttle service. We waved to each other, as we crossed on the B4632.
At Stanton we already have quite a few piles taken there on an earlier tidy up day.
The new piles went in on the opposite side. Brambles and rain won't hurt them, they're pretty much indestructible. If we need a set, we can always dig them out.
We also took 10 - 12 bags of accessories for these pads. They're in dumpy bags.
We got them there - just. Some were creaking badly on being lifted; they decay quickly under the sun.
On the other hand, here was also an opportunity to take away 12 pads for a crossing that we want to build. That's why we have LT storage.
This crossing is for the top of the Working Lane approach, where Stevie Warren once laid in a sleeper crossing, that we had to take out again later. But it was useful, so we will now construct a proper one.
Here are the 12 pads being dropped off at Winchcombe, from where our RRV will take them to the work site through the tunnel.
Next came a vast collection of cast iron chairs, removed at Toddington from expired wooden sleepers. We took those down to the PWay yard at Winchcombe, where we have others.
Two pallets of GWR throughbolters were taken to the 2807 foot scraper site.
The final two van loads were sundries - more chairs, a pallet of bearers, another of chair scews, an old sack truck, a picnic table, and a bunch of cheap suitcases. All have been found a new pupose, and on top of that, they are off the greenhouse site.
Here is what we left behind (we also took that last pallet) - a nice tidy corner of the site.
There is more to go - piles of concrete sleepers and FB rail (Ex Bicester) mostly, a much slower job.
There are also a couple of hundred 'wartime economy' sleepers, out of the nearby Didbrook relay. Sixty of these are scheduled for the final part of the 'siding 2' relay at Toddington.
 |
| House and attic clearance - Man with a Van! |
In passing, we took a snapshot of the 'new' drive, which is due to be moved left here, up against the fence.
Some prepatory works for this were already done at the top by the entrance
Now a post and rail fence has been erected across the intended new line. Strange.
The all important gas main is marked by the red and white post lower centre, and it pretty much runs along the white line on the right.
Last thing for Friday: An advertisement.
We have a small trailer and a turnstile for disposal.
 |
| Small trailer, surplus to requirements |

This is the turnstile, in good condition, with maker's plate. This used to separate the garden centre from the GWSR entrance.
Any interested parties, please send a blogger contact form.
Sunday and Monday at Broadway.
Painting, and on Monday, riveting.
We came in on Sunday, exceptionally, as it was a bright and sunny day, and a good opportunity to get more painting done. It's going to be a wet winter, they say.
Expecting two steamers on Sunday, we were surprised to see the 'Bubble Car' arrive first thing. We overheard a snatch of conversation from down on the platform - 'why do they call it a bubble car?'
A good question - who knows the answer to that? Was it because it was much smaller than a two or four car unit?
We painted all day, a rather tedious job. Most of the steelwork already had an undercoat of sorts, but under the greenhouse it was impossible to get every bit painted, as some of the steelwork was piled on top of each other, and other (heavy) items could not be turned over in the small space available. Then there was blowing sand, sawdust billowing, oil spatters from drilling, and steel drilling residue going rusty. So what turned up at Broadway wasn't brilliant, in terms of paint. On top of that there were a lot of holes in the paint due to transport, lifting and handling damage.
Monday saw three volunteers back on riveting the platform side fascia board. Here is a rivet being heated to just the right temperature. The hot rivet is then grabbed with a pair of pliers and handed to one of the two riveters, who insert it into the hole. Seconds later there is a brief Rat-a-tat-a-tat, and the rivet is in.
While painting undercoat on Monday, we also kept a wary eye on progress with the rivets, and would dart in with the green undercoat to apply it to the bare heads, once cooled. Later in the day we were even able to apply undercoat, so this is what it all looked like.
On Monday riveting of the fascia boards was completed. As an example, there are 20 rivets attaching the fascia board to the truss, of which there are 4. So all in all we just did 100 hot rivets. Another couple of dozen await doing, then that job is complete.
Tuesday at Broadway.
More good weather, so back on top to finish off the painting. This we did, and the entire steel structure now has a protective undercoat on it.
Doesn't it look magnificent, in its new coat? Only the platform side of the fascia board is as was, and it's not at all clear how we will paint that. Maybe when we fit the dagger boards there?
Neal had made up some more brackets for the woodwork. Our remaining materials, after the big lift, were suddenly cleared away from the Toddington greenhouse area. This comprised new angle iron, woodwork, and two 5 inch steel pipes for the future modesty screen. We had no idea.
All the steel was sent to the metal skip, while the woodwork ended up at Winchcombe.
By a miracle Neal was able to retrieve it all, after some detective work. Doesn't help your morale though.
The brackets, made up out of the new steel nearly scrapped, still had mill scale on them, so we spent the day grinding that off, and painting them.
Neal is making really good progress with the woodwork.
The idea is to get at least some of the roof on, so that we have a dry area to work under.
The timber on the end is for the triangular end panel of T&G.
Here he is drilling fixing holes for the chamfered timber that supports the corrugated iron sheets.
We don't have the glazing yet, but have found an acceptable supplier, after the previous one (P1) ceased trading.
This corner shot shows the other extremity of the end panel support, as well as the support structure along the rear fascia board for the dagger boards and cast iron guttering.
At the end of the day the 8 brackets (on the floor) were primered and in undercoat. Only a short length of chamfered timber remains to be fitted to the purlin on which Neal is working.
Usketeers.
Cancelled this week, due to personal circumstances, and the poor weather foreacast. Back next week though.
Wednesday on the PWay.
Pictures by Paul.
The poor weather may have deterred the Usketeers, but the PWay gang wrapped up in their best winter gear and got to work nonetheless.
Today it was at the north end of Gotherington loop.
It's a pity that the Usketeers weren't there, because the two groups could have met up - they were working only 100 yards away.
In fact in this picture you can see the little ground frame hut centre right, but no one near it.
Usketeer Paul was considering getting his frying pan out again for some bacon baps, and on this wet day he would have had several eager takers, next to his own gang.
By lunch time in fact the rain was starting to die down, and PWay gang lunch was taken on platform two, in full view of Bryan's lovely Gotherington station.
After lunch it was time for a bit more working, tamping with the Robels. It seems only fair, after all those doughnuts.

Some might ask: where do all those doughnuts come from, out in the middle of nowhere?
The answer is: this plastic box. It contains all the snacks that we have, some new, some a lot older. Those are for the bold, and the very hungry.
Unfortunately age got to it eventually, and the PVC started to crack up.
After a WhatsApp group appeal, Peter was kind enough to let us have a new one, a spare that he had.
Today's yummy: Mince pies.
Already ???