Thursday at Broadway.
No trains on Thursday! That was a surprise, and a bit of a disappointment, as it is always a pleasure to spend 20 minutes in the cafe after the first train has left. So it was vacuum flask coffee only, not Cappuccino.
On Thursday John returned to the rear , where you see the first course of the day going up.
That was No. 16, with No.17 applied in the afternoon.
Besides making mortar for John, and shuttling backwards and forwards with supplies of bricks, we also continued dealing with the large (but now substantially reduced) pile of broken bricks under the footbridge steps.
These broken bricks, mostly from the original waiting room but no longer useable, are reduced to rubble bit by bit. This rubble is then used around the building to improve the ground under foot. We will be grateful in winter, when the clay gets sticky again.
The other daily activity is the cutting of bricks into halves, for the make believe headers.
Thousands are needed. But we do 50 - 100 a day, and have so far kept pace with the laying of them.
Specials also need cutting. This is to make them fit around the doors and windows.
At the end of Thursday John had reached course 17 on this half of the back (the end is up to course 20).
It's starting to look quite enclosed in there.
Good Friday at Broadway.
There is no stopping the canopy gang, even on public holidays. For yours truly this will be an exceptional 6 day week on the railway. Is that what retirement is like? We only worked a 5 day week before... It must be because we enjoy working in a team that achieves something (this includes PWay and the Usketeers BTW). Maybe you would too? Come and find out during one of the Trust volunteer team events, which take place every month - https://www.gwrt.org.uk/volunteering/volunteer
Heavy rain was forecast by the Met Office, light rain in the afternoon by the BBC. Who was right? We thought we would make a cautious first mix, and then see. In the end we made three mixes, one more than normal, and no real rain ever came.
John continued along the back.
In the distance we heard the first train of the day coming, by the fact that it was blowing off.
It blew off past the goods shed, and into the station.
It blew off at the end of the platform...
... and carried on blowing off on the loop points.
Safety valves finally closed again, 3850 trundled past the P2 work site.
While John was laying courses 18 and 19 along the northern half of the back, Neal busied himself around the site, and we see him here with a laser level on the corner of the building.
This was, we ascertained, to check the height of the two columns that will be planted at the bottom of the staircase. (replacing the two temporary RSJs there at the moment.)
Looking at the building - for that is what it now is - from the end, we can see quite a substantial wall on the right. This will be fitted with poster boards in due course. It will be the first thing you see when you come down the stairs.
Being Easter, the station was quite busy during the day. We took this picture to give you an idea of the crowd waiting for the incoming train.We couldn't help noticing this Mk.1 in red and cream, with its authentic BR 'Ferret & Dartboard' crest. Isn't it wonderful? It's beautifully restored, a real credit to our C&W department. First class too.
Saturday, out with the gang.
Just the six of us on Saturday - this number will have been impacted by grandparent duties. It was Easter Saturday, and the 'Easter Eggspress' was out and about.
Here it is, picking up the token from Toddington signal box, watched by an assistant.
With the section of track on siding 2 cleared on Wednesday, we were able to start digging out the bed, and relaying with the Didbrook economy sleepers.
It's great to have mechanical aids, but in the end it's Joe Soap (or here, Jim Soap) who has to finish off the excavation by hand.
You can't escape the shovels...
Getting ready for the relay were Leigh and Dave (in the Telehandler). They brought supplies of economy sleepers from the garden centre site down to the ash pit, from where they could be loaded on to the RRV trailer.
Here is Dave in the Telehandler, loading what he had previously brought down on to the RRV trailer.
Soon the first sleepers were being laid into the scraped out trackbed. (missing is a lengthy period of scraping, where we tried to work out if we had scraped deep enough)
While getting some more tools we deviated via the loco shed to see what was new:
Over the last couple of days he has been happy trying it out on the 4 trusses for the Broadway waiting room.
Once the ends of each truss have been bent to the correct angle, the parts have to be drilled, bolted together, and eventually riveted in situ.
Once assembled on site, together with the purlins and fascia boards, they will be further rivetted all together.
A bit further along is a Great Western cab being made.
Is it for children to practice on, or is it for a locomotive being restored from a Barry wreck?
The green rings around the window cut out are originals, all that could be saved from the cab, after all its years at Barry and a hillside in Blaenavon.
Behind that is our own Bubble car. It's got a lovely coat of paint on it, but the interior still needs completing.
Working on it on Saturday was a man from C&W who specialises in Mk1 door locks. All the locks need revisiting. Too loose, or need a boot to open them. That won't do, but they are in experienced hands.
When will it be ready then? Some time in the autumn, was his unofficial opinion.
Then back on site, where more scraping was going on. The first 8 sleepers were down, but after that the ground seemed to rise. Or did it?
Unfortunately we do not have a laser level for this sort of thing, so it was done by eye.
Time for another shot of a departing train. Here it's 7903 Foremarke Hall, having just picked up the token for the next section to Winchcombe. It's a cautious departure, as the station limits section (max 10 mph) is quite long.
Finally we had a full length of sleepers in, although these rail lengths are shorter than usual for some reason. When they were laid back in the 1980s they came from all sorts of places, but mostly sidings, where they were already well worn.
We lifted the first pair of rails back in, always a satisfying moment.
Construction is better than destruction.
In the background STEVIE is scraping out the next section.

By this time in the afternoon it was the turn of the daily diesel locomotive to take the train south.
It's a nice human moment to see the signalman handing the token to the driver, with a second person in the box looking on.
Tuesday, back at Broadway.
An additional day of brick laying, with just the two of us on site.
John was laying on the second half of the rear. He put down two courses, but has not yet reached the height (20 courses) of the northern half.
Keep plugging away, John !
Wednesday with the Usketeers.
A full complement, plus visitor/supporter Mike.
Most of the day was spent fitting the slates to the skirting board level, and then around the inside of the fireplace, which also had symptoms of damp - possibly from above, through the open chimney.
We went around the bottom of the fireplace, before doing the rear and sides.
This shot shows pretty much how far we got. Just the sides still to do, then we can mortar in the bricks that will form the bottom (stacked on the right). At the same time we can do the doorstep.
Well, you only had to wait a bit !
We also rescued an enamel sign from the old shed being demolished. We heard that the old Building & Services shed was actually put up by the builder Cook, who used to occupy the yard before we sold him a parcel of land on the forecourt, on which he then built his own offices. These we (much) later bought back again, and the building became our new HQ under the name Churchward House.
In the picture is visitor Mike, admiring one of the trusses for Broadway, now complete and fully rivetted. Well done, Neal! (and friends)
PWay on Wednesday.
These pictures were taken by Walt and Paul, so thank you both.
The gang was in two halves today. One was sorting out sleepers in the garden centre yard, and loading them, the other was busy extending the relay along siding 2.
The rail head was where we left off on Saturday, with 1 1/2 panels laid. During the day a further 3 panels were laid in, and the excavated trackbed considerably extended.
With the train out of the way, work could resume - digging out in the background, and filling in the old ballast again in the foreground.
STEVIE (operated by Walt) had quite a sucessful day. The RRV not only dropped in all the sleepers and rails for 3 panels, but also dug out a large part of the formation, almost back up to the goods shed. This is where the panels that we relaid, together with the new stop block, stopped last time.
Finally, a quick peep into Andy's car boot, to show more supplies of rail ends that we sell. It is amazing how popular these are, they are still selling well, and these sales (plus some generous donations that we have had) are making it possible to order several Milwaukee PWay tools. We can't wait to start using them.
You can buy the rail ends from the Cotswolds Halt lobby. They generally come in door stopper or anvil sizes, and come waxed or painted.