Friday at Broadway.
Dull and icy cold, due to a mean northerly wind. Nonetheless all three canopy gang members were working on site.
On Thursday Neal managed to get all the remaining dagger boards on along the front. They give the new building a fuller look. With canopied buildings on both sides, joined by a covered footbridge, we're struggling to think of another preserved railway station like it in the UK. Broadway is very special.
The damp humid atmosphere did not lend itself to painting anything outside, so we did these brackets that Neal had made, and cleaned by us a few days ago.
Neal explained that they are not part of the original design, but will allow some sort of divider up under the sheets.
At the end of the day they were still pretty damp, due to the humidity outside. They need a bit of sun. Should be dry by Monday though.
With the front dagger boards up, Neal readied himself to fitting the mouldings, and the dark stone fascias that will hold the guttering. He asked for 12 of the mouldings to be fetched from the centre of the scaffold, and dropped down to ground level. The woodwork prepared at Toddington is now basically out in the weather. It's partly covered by a cheap tarp, the woven kind, which lets the water through if pushed. Everything was certainly wet underneath.
Neal wanted the mouldings down so that he could cut an angle into the ends, allowing them to fit together when mounted lengthwise.
We then brought the mouldings, once trimmed, back up, and Neal spent the day nailing the red fascia board, a small and a large moulding all the way along the suppporting woodwork attached earlier in the week.

John was also there, and spent the day working on the first row of the four corbelling specials.
Below you can see one of the arches, which are already well enveloped by the brickwork rising above it.
In this picture you can see Neal attaching the three layers of boards along the length of the platform.
He spent the whole day slowly working his way along.
This shot shows in greater detail what Neal was attaching - a red board on top, which supports the gutters, then a small moulding, with a wider one underneath.
Over lunch we had a quick peek in the signal box, where the S&T gang is prepping for an inspection the following week.
Note that the levers have all had their lever leads applied. Sadly not in brass, the company can't afford that.
So this is the famous 'Acceptance Lever'. It's the one on the far right.
It does mean that there is no token machine, or token exchange on the platform.

As the light began to fail, Neal had almost arrived at the end. Just one more length of each to fit. He was pretty proud of his achievement.
Here he is, telling Sam (our head of S&T) something about the tumultuous time we had getting the station built in authentic style. But we got there !
Monday at Broadway.
Icy cold now, frost everwhere when we arrived.
Our second week benefitting from the S&T possession is not in fact 5 days, but only four. There is a train to Broadway on Friday. We'd better get a move on then.
While you can see John at work laying corbelling bricks, Neal set to work to finish off the mouldings. Just a bit of cutting and trimming, to finish off the last few feet.
Yours truly was unable to paint. It was dry, but much too cold, and the melting hoar frost made the structure wet again. We decided to tidy up the site a bit, by bundling up 4 disused and sunbleached dumpy bags, and putting them in the bin with other floating rubish. They were too fragile to be re-used.
Neal pushed this a bit further, and suggested we rid the site of all the unused pallets. That was quite a job, they were scattered about everywhere.
Eventually we got them all in piles outside the building, and went to fetch the tail lift Transit.
With Neal's help we managed to get all the pallets on board, and a couple of ratchet straps to hold them down.
The destination was the lighting up wood area behind the diesel shed at Toddington. To our relief there was plenty of space, so we dragged all the pallets off the truck and piled them neatly behind the Heras fencing.
A quick count afterwards revealed that we had cleared the Broadway building site of 40 pallets!
Leaving Toddington again, we came across a mini digger with an external contractor. They had dug a smallish hole on each side of the main gate - one by the platform entrance, the other by the old collection postbox.
Wonder what they are up to?
After returning the truck to Winchcombe, we called in at Broadway as the light was beginning to fade.
Here we found Neal and John just wrapping up.

To our delight we found that Neal had indeed started on the first two of the roof panels. They are black on top, and light stone underneath.
If you look carefully, you can also see that Neal has fitted the first length of gutters.
John is just finding that it is dark under there now.
As readers may recall, the waiting room only had windows at the front, so with the canopy over that it will be relatively dark inside the new waiting room. We haven't picked on any lighting styles yet, but would be looking for something that appears to be lit by gas or oil. If readers have any bright ideas (joke intended...) for UK websites with suitable styles for 1904 lighting (with modern electric power) we'd be interest to hear.
Tuesday at Broadway.
Just two of us, but a great day for mounting roof panels.
These corrugated iron panels are powder coated and very delicate to manoeuvre round the top of the building. They are heavy, awkward to handle, and easily scratched. There are obstacles everywhere.
It took 2-3 panels, but after a while we settled into a sort of routine where Neal was based on the tower scaffold, and Yours Truly on the building, handing him all the different things he needed to get those panels on.
And the guttering below, which had to be fetched from the container and lifted up on the main scaffolding.
We have a supply of 5 inch cast iron gutters, left over from the P1 build, but it's not enough for the whole P2 building. Hopefully it will at least reach to the end of the platform side.
It's really practical to be able to attach the gutters at the same time as the first row of sheets, using the tower and S&T's track posession.
Two more days to go - that should just about be enough.
In other news, John was able to complete laying the first row of corbelling specials. The built up corner shows you which type of brick is next, for each course.
We also had the opportuinity during a quiet moment to give those steel angles a second coat. It was actually quite sunny at one point, against all the forecasts.
And, oh yes, greetings from the canopy gang. We enjoy what we do. Neal was feeling very chipper.
Here you can see him attaching another length of cast iron guttering.
After each new length, we have to get down and move the tower along a couple of sleepers.
Thanks to the dry (but cold) weather, we were able to make steady progress.
At the end of Tuesday we had this much left to do. That'll be for Wednesday and Thursday. Thursday is S&T's Broadway certification day, and Friday sees the first train again.
As the light faded we see Neal putting in a few screws along the top edge. We put in 13 panels today, and have arrived one panel short of the half way point. There are 16 to go, plus a bit of complication near the half way point where the joint for the downpipe will be. That is signified by two daggerboards that have been put in lower than the others.
Every day this week the full S&T gang have been beavering away at Broadway, even as it got dark. Both the ground frames have been cleared away, so the turnouts must now be operated from the signal box. There was still a lot of snagging to do.
As we left at 16.30 Broadway box was lit both on the operating floor and in the locking room.
These lights have never been seen before. It could be quite atmospheric with that first train on Friday. It's goinmg to be one of several late afternoon shopping trains, to see the lit up High Street at Broadway. A great initiative.
Wednesday at Broadway.
The penultimate day of the track possession, and we are doing our utmost to make the best of it. As Wednesday is Usketeering day for Yours Truly, Neal realised that he would be unsupported that day, and he could not manage fitting the roof sheets alone. Given the urgency, and very hard to get track possession, we agreed to forego cake, Hamburgers and excellent company for once, and stand on a windy, ice cold scaffold instead.
There were 16 sheets left to place, and today we only did seven, as the guttering needed a lot of attention in the area of the downpipe collector.
Here Neal is indicating where the pipe will go through (!) the steel fascia board. The two dropped dagger boards indicate the place.
This is the collector, together with an elbow that we found in a cardboard box in the container.
Quite a few visitors turned up today.
We are always happy to explain what we are doing. However, when you have spent 10 minutes with one couple explaining the drainage system another couple turns up, and this bites seriously into our precious track possession time.
John was also there today, making it a fully manned canopy gang. John made a start on the second of the 4 corbelling specials courses along the front, and got half way during the day.
We thought you might like an update on what the interior looks like these days, so here is a shot of it today.
It's still very wet in there, as we don't really have a roof yet.
All the interior walls are up, and the beams for the ceiling are in.
The two fireplaces are half built, in concrete blocks. The breasts and chimneys still need doing.
Late morning Neal was finally ready to fit the first roof sheet of the day, after spending a lot of time on the collector for the gutters, as well as some realigning of sheets previous fixed.
Getting the sheets from the pile to the area where Neal is working is a delicate task, there are so many pitfalls on the way.
They also come off the pile upside down, and the wrong way round. Who knew....
The sheets we have already done look quite impressive (and dry...) from underneath.
We have a total of 30 to do along the front, and perhaps 100 sheets in total to put on the roof.
It's not only sheets of course, quite a big area is glazing as well. We're doing the sheets first.
We had to leave at 3pm for a meeting, but it was already getting dark anyway. Today's tally was 7 sheets, leaving 9 to do on Thursday, the last day of the track possession.
Here's a little puzzle for our readers:
Which locomotive could have inspired the artist when he designed the sticker for the windows of our Santa trains?
Usketeers on Wednesday.
Pictures by Jules and Dave, as your blogger can't be in two places at once...
Today's job was the placing of the sleeper end at the front, as a base for the return wheel for the signal operating wire.
The original sleeper was rotten. This one already has an Usketeer history, as it's an off cut from building the lineside hut.
Waste not, want not.
Here the hole is being excavated.
Here the wheel has been bolted back on, and the wire now engages with the wheel, coming right out of the little mousehole we drilled last week.
There will be some pulling force on this sleeper, so we have arranged it so that it butts up agains the cabin frame. Some wedges by the track sleeper were also used, but the complete setup has not yet been tested.
After lunch, the pulley at the foot of the signal post was investigated. It was rusted fast.
A decent dose of W40 should solve that problem, we will see next week.
The week after is the Wednesday on which we will have a small ceremony with Bryan and Savita.
PWay this Wednesday.
There were two gangs out on Wednesday, one working in Greet tunnel, and the other, smaller one was spot ballasting up by Stanway viaduct.
Here is the team by the viaduct, using those second hand dumpy bags to drop a 'just right' amount where it's needed.
STEVIE once again proves his worth. Formerly this would have been a wasteful DOGFISH load costing £100s, and a diesel loco with a rostered driver an d guard.
We do it so much better now.
BTW That looks like an enormous tank wagon, maybe with bogies. Is it new? Does anyone know more?
The other, bigger gang was working inside Greet tunnel. Although it's mostly dry in there, a surprising number of sleepers have had to be marked for replacement. Andy Smith took this rather spectacular picture. You can see that this was once double track.
We now work with modern LED lights, and if we are not mistaken, it is no longer necessary to bring along a smelly petrol generator to power them.
Here you can see one of the replacement sleepers being clipped up.
Behind, by the refuge, are streaks of moisture with point to leakage and wetness in the ground. This seems to happen mostly at the ends.
While on the roof at Broadway we took a phone call from the gang - can they now use the lineside hut that we built?
Of course, we said, it's not just a pretty picture for photographers, but for actual use. They were impressed by the carpet strips on the sleeper benches, and managed to get 8 men in there. A ninth was posted outside.
The Usketeers who built this were rather chuffed. They not only got it funded (with blog reader help for the sleepers) but also built, and now used as well. Good Stuff !

































































































