Wednesday, 22 November 2023

Broadway planning amendment agreed.

Friday at Toddington.

More work on the steels. In a break from the monotony of that, we had the company of the shotblaster during the morning, and the comings and goings of race trains during the day, always welcome this time of year.


 

 

The shotblaster started work on the long fascia boards, which had so much tough millscale on them.


Neal, John and Yours truly hurriedly re-arranged all the other steels so that he could carry on at a reasonable height.



A short while later he had moved on to the supply of angles, with which we will be building the trusses.

As you can see they are up on trestles, making the shotblasting a little more comfortable.

In the foreground you can see more of these angles - we have about 40 of them. They greyish patches are the millscale on them, the rest is rust.



 

 

A pleasant surprise on Friday was the discovery of 3 of the purlins set to one side, and already fully rivetted! All the bolts have been replaced by permanent rivets. That will save a lot of time later on.




 

Friday also saw the first of the race trains, a very welcome piece of commercial activity in this, the low season.

At lunch time we photographed the 2-6-2 visiting tank 5526 returning with the ECS from CRC, ready for a return to pick up the happy Cheltenham punters at the end of the afternoon.

Private helicopters roared overhead....

The shotblaster was done in just two hours. We were lucky with the weather, and immediately set about painting all the bare steel in primer to prevent the early onset of any rust.


We had a very pleasant visit and chat from Richard, a blog reader and, as it turned out, a supporter of the slate fireplace in the cafe at Broadway.

Neal was happy to explain where we were with the P2 building plans.

As it happens, we have just been advised that our request for an ammendment to the earlier planning application had been agreed. That's another step behind us. Some paperwork issues have also been resolved, and at the moment we are negotiating to hire in an excavator (more complicated, it turns out, than it used to be). 

Given that the planning is now agreed, we can show you the final design. We hope you like it!

A bit of background:

The P2 building formed part of the original planning application for station building, P2 building and signal box. However, the design was that of the non-railway enthusiast builder, and was not very true to the original shape. (Different roof pitch, slate roof covering, not connected to the footsteps for example). We will do better.

It has always been agreed that the building would be slightly bigger than before, because the P1 building is 50% larger due to the extra toilets. This will keep the P2 building in proportion. A constraint to the exact size is the position of the trusses. What we have done is add one extra truss, and so add 7.25m to the length.  Trusses are at 7.25m centres. From the platform you will now see the original configuration of doors and windows, but twice. That will give two rooms inside, each with its own fireplace (and two chimneys instead of one). The dividing wall will not be structural and could be moved at some point in the future to suit requirements. Initially we see the rooms in use as a waiting room, and a museum space. Currently the railway has no museum space (RATS coach excepted of course)

The roof will be of the same riveted construction as on P1, and it will form a canopy overhang at the northern end to the bottom of the staircase, but this time in perfect alignment with the building. At the other end we will recreate the shape of the former gents' toilet (omitted before) with a flat roof and modesty screen. As we have ample toilet capacity on P1, this room will become a store for station maintenance,  such as mowers and tools. Recreating an actual toilet here is not really feasible as there is no foul water drain, the original urinal simply having had a soakaway.

So that is the state of play with Broadway P2 at the moment. There is no Trust appeal for it as such, as that would compete with the ongoing appeal for the viaduct repair. However, the Trust can only support so much, so if you want to help the Broadway P2 building, a donation (with gift aid option) to the Trust will definitely help. The Trust is supporting us, but the security of the viaduct must come first.

https://www.gwrt.org.uk/donate/how-to-donate

 This is a link to the Trust's donation page, if you'd like to help.


Back at Toddington on Friday, and as the sun began to go down, our visitor 5526 set out to collect the happy punters from CRC in the late afternoon.


We waved it goodbye as it chugged off into the distance, then resumed our primering, of which there was a great deal to do.





Saturday along the Broadway extension

A good turnout of eleven, on a very damp and windy day. The afternoon was supposed to be dry, but it wasn't.

 

Something that struck us straight away in Winchcombe was that the work for the S&T workshop has started. The site has been fenced off and marked out. 

We had seen plans for a 3 road carriage shed up to this point, and a large building here grabs a good part of that space.

Our plan for the day was a repeat of last week - elimination of minor faults from the viaduct to Broadway. It's all concrete sleepered track, so not a great deal to go wrong except loose clips, and the occasional concrete sleeper crunched by tamper tines.

You can see the sort of stormy weather we had from the picture above. The scene is a foot crossing north of Stanton Fields. (MP7.I) The van couldn't go any further, so the tools had to be carried quite a long way.

The short straw for carrying usually goes to the newest recruit. Here it's Peter, laughing (well, he's still new, isn't he) as he carries a Duff jack for about half a mile. Probably not laughing any more when he reached the truck...





Lunch was held on Little Buckland Bridge.

This little hard boiled egg bears witness to our presence, although only insiders will know why it was there.

It's a mystery egg...







Tuesday on steels.

A bit of a miserable day - grey and with drizzle. Luckily there was little wind, so we were able to paint.







The shotblasting was only a partial success as the medium used proved to be too soft.  

Here Neal is having to follow up with more manual grinding, to get things properly clean.


John and Yours Truly spent most of the day (after an extended reshuffle of all the steel, once again) on giving the angles put into primer on Saturday an undercoat.

You might see two shades here - we ran out of dark stone undercoat, and decided to use a slightly darker, redder shade from a big tin that Neal got at a car boot sale (his speciality....) for about 10% of the normal price.

We are very keen to keep costs as low as possible.



 

This is what we've got left to do, a vast expanse of primered angles, with some not yet ready to receive any paint at all as follow up cleaning after the shotblasting still needs to be done.

You can see streaks of rust here.



 

 

Elsewhere we noted that the WARFLAT had been pushed out on to the unloading road.

This needs unloading, so that concrete sleepers can be loaded at Winchcombe for the viaduct relay. We're not using the old wooden sleepers.

When we had finished rearranging the steels in the morning, PWay manager Paul appeared and took over in the Telehandler. He neatly stacked the sleepers with the others that came out earlier, and then loaded on to the WARFLAT two long timbetrs, brand new, that has been lurking in the garden centre site (mysteriously, but we don't argue about free gifts).

A small update from the viaduct - no pictures though - is that the contractors have cleaned all the infill off now, and reached the top of the arches. It was suprising to see how shallow the spaces between them are - it's just a series of gentle undulations.

So good progress there.



Wednesday with the Usketeers.

As we are now building a fence requested by the railway, we got a small grant from the Trust to cover the cost. A purchase order was issued, so we went off to the fencing companyy to collect the order.

Things didn't quite go as planned... as a precautionary measure we called in at 8am to check they had our PO, and that we could come and collect. We could.

We turned up at 11am and cash was demanded, as the railway didn't have an account there. But you said it was OK to come and collect the stuff? Yes we did, but only if you pay!

Ah well.

We put the wood in a dry place, as it was all wet and not ready for creosoting yet.





In the meantime Walt and Chris loaded 5 concrete sleepers onto the RRV trolley.








STEVIE rolled by with its precious cargo in tow.

The destination, we ascertained, was JJ  Farms bridge, where a number of concretes need replacing. Now is a good time, as changing a concrete sleeper is a big job. Luckily there are no trains until the Santas start.



Back at the ranch we caught Paul making the second hand gate ready for the site. He did a grand job shortening it, and it is now 10ft long instead of 14ft, with a little support wheel at one end.

The next adjustment rquired was to the hinges, which annoyingly didn't fit the post that we had. So much for standardisation. It meant that one of the hinges on the gate had to be moved about 3 inches.




Dave and Yours Truly spent most of the day making the site ready for the gate and fence.

It's also the intention to move the compost bins to the PWay yard, to be out of the way of any visitors.



In the way of the moving bins are still remaining piles of earth that have been shoved up against the fence.

As we also need fill to complete the site levels, we used one problem to deal with another.

Here is Dave in the Telehandler with a bucket load.



We cleared the area where the new fence will hit the edge of the site (next to the bins), then moved round to the other side of those bags (Who put them there? Oh, we did...) and took out several more useful chunks of spoil.


 

That spoil was then dropped where the fence line will run. We now need to level it out to make a gentle slope, and then cover it with what remains of the topsoil under the tarp.

Then it can be seeded.

Near the end of the day we saw Paul again, this time at the hinge end of the gate.

Moving the hinge interfered with a cross member of the gate, so to keep the stability Paul screwed in an extra support.

When he's finished the whole thing then needs to be creosoted (or Creocoted, we aren't allowed to buy the real stuff).

Autumn is now clearly here, as this picture of our oak tree shows.

We learned yesterday though that the Macaw will not now be moved to the stop block, so sadly the Usk hut will continue to be obscured from P1. It is felt that the guards van should be at the end of the rake.

As we left the yard we took this updated picture of the S&T building works. The foundations are going in here.



16 comments:

  1. You certainly keep busy!

    Brake Vans were never left occupying the off load platform space, they were kept on a separate siding, ready to be used.

    Malcolm

    ReplyDelete
  2. Great to see the P2 building as it will be, if only in outline as yet- and 2 fireplaces! Love it!
    It's not hard to imagine that the steelwork must feel like the labours of Syssiphus, right now. You're all heroes in hi-viz!

    ReplyDelete
  3. Love your blog. Are there still plans for a carriage shed?

    ReplyDelete
    Replies
    1. Five years ago a plan was drafted for a three road, 8 coach carriage shed round the back of the existing C&W workhop. It wasn't cheap though.
      Maybe if we get another legacy...

      Delete
  4. Who needs a Loo on platform two , Sorry , but P2 looks good and sensibly bigger .
    The Carriage shed is still miles away due to money needed for the viaduct which the Trust are funding , not the GWSR . Tough times ahead I’m afraid . John M.

    ReplyDelete
    Replies
    1. Is the Trust not part of the GWSR? News to this trustee...

      Anyway, great news on P2, very pleased this can go ahead now, and that the money is still available despite difficult times.

      Delete
    2. Technically the Trust is not part of GWSR - but they are very good friends.

      Delete
    3. A matter of philosophical debate I suppose :) I've always seen it as GWSR having constituent parts; the Plc and Trust primarily, and others including RATS, rolling stock owning groups etc. Ultimately, GWSR is the people, the structures and companies are just what makes it happen.

      Delete
    4. From the GWSR website: The Gloucestershire Warwickshire Steam Railway plc (GWSR) operates the railway, which is owned by its shareholders. All the working staff of the railway report to the GWSR, and nearly all are unpaid volunteers who must in addition be current members of the Gloucestershire Warwickshire Railway Trust (GWRT).

      The day-to-day operations of the plc and the Trust are in the hands of boards of directors that are elected by their respective shareholders (or members). Coordination is facilitated by having some directors who sit on both boards. The management team at the GWSR sets the strategic goals for the railway, and directs the activities of the volunteer and paid workforce. The Gloucestershire Warwickshire Railway Trust (GWRT) is a Registered Charity (No. 1133186) and a Company limited by guarantee. The aim of GWRT is ‘to maintain and develop a railway museum for the benefit of the public, buffer stop to buffer stop, fence to fence’. GWRT does not own any infrastructure or operate any trains.
      My understanding is that the GWSR plc is not a charity but the GWRT is. We have a similar set up with 2807, which is owned by Cotswold Steam Preservation Ltd but supported by the 2807 Freight Loco Assn, which is a charity.

      Excellent news on the progress with the Platform 2 building btw.

      Delete
  5. Yes, I add my praise too that the P2 plans amendment has got the go ahead. Got there in the end! Will we be having the Broadway camera relocated so that we can keep up with the construction as it happens?
    Regards, Paul.

    ReplyDelete
  6. What will S & T's new workshop look like when it's finished ? Will it follow the GWR architectural vernacular, or will it look like an industrial estate unit ? David

    ReplyDelete
    Replies
    1. Sadly, general volunteers know nothing about the size and shape of the new workshop.

      Delete
  7. That was going to be my next question: are there any plans,drawings artist impressions iin the public domain ? S & T are keeping their cards very close to their chest. David





    ReplyDelete
    Replies
    1. We know nothing at all. Possibly no planning required, as a railway building.

      Delete