Wednesday 22 June 2022

A summer week, and a special train.

Saturday out along the line.

A gang of 8 on Saturday - very good. We split into two units. One stayed behind to service the Robels, the other went out along the line with the Interflon equipment.

Bert Ferrule in between the platforms.


 

Four of us then went up the line through Winchcombe station, greasing the fishplates with the Interflon backpacks.

Last year we removed the fishplates on each occasion; this, the second, year we can do it more simply by injecting the grease around the fishplate, and it will work its way in. Interflon is expensive, but the process is now much faster and the team more productive.






We worked our way up the line to Greet tunnel, where Bert took a snapshot of Tony.

These backpacks have been giving us trouble, as at some point they cease to work, we think because of some internal blockage due to the Interflon separating.

 

 

 

 

 

 

Neal from the canopy gang - he's really good with his hands, as readers surely know - kindly volunteered to examine the backpacks, and on Saturday we got both back again, in 'running condition' as it were. Thanks, Neal!

 

 

 

 

 

 

 

 

 

At the tunnel mouth we noticed that the sign for Greet tunnel had been refreshed. It looks much more authentic now - we like it!




 

 

With two operators equipped with the backpacks we were soon finished with that stretch of the line, so turned northwards instead. The job was to grease from Greet tunnel to Chicken Curve.

As we passed through the yard area, we stepped aside for a passenger train, here headed by P&O.

 

 

The crossing train was headed by Dinmore Manor, blowing off steam as it left the platform.

The safety valve stayed open all the way to the other side of Chicken Curve, which seemed strange to us. Was it stuck perhaps?





During our early morning tea we learned that check rails on turnouts are best keyed up with oak keys, as these do not compress and don't give way to sidewards pressure. We had never seen that before, but an hour later we saw exactly that - new oak keys on a check rail. You never stop learning on the railway.



Chicken Curve was easy to grease, as the rails were all of 120ft lengths, so we went twice as fast. We were soon back by the mess coach, where we met team 2 servicing the Robels. They were getting special motor oil, and the bottle explained what fun it was to ride on a fast motorbike. Oooh - can't wait to use the Robels again now!



 

As we paused for our lunch, Dinmore Manor rolled to a stop by the bracket signal, once again blowing off.


As it was much cooler on Saturday (16 degrees) than on Friday (30 degrees) you could see the smoke and steam particularly well.

 



After lunch we went to Broadway to grease the first section there. We just managed to dodge a large shower, so it was still dry out, but large clouds swirled around.

Dinmore Manor backing into Broadway by the bracket signal.



Up by the goods shed you should be able to get a good shot with the bracket signal in the picture. There were also some fine marigolds in patches in the grass.

We lined up this shot with the Peak.

Photographer's luck - the driver sounded his horn on seeing the PWay workers, and we are required to acknowledge the signal by raising an arm.

That caused the camera to wobble, and a late shutter release.

Oh well.








Tuesday at Broadway

A week of lovely sunny days. We've decided to work at Broadway on Tuesdays, when trains are running and the cafe is open. We are on the P2 steps and out of the way of the public.

We had the pleasure of a visit from the Ivatt, 46521. It's nice to hear a different whistle in the distance and rush up on the footbridge to see what is going to arrive.

Neal wanted to see it too....

One of the things on our to do list is a set of fire buckets for the northern end of the building. They will fit neatly under the window.

While we found quite a few of the specially shaped fire buckets (and then expertly painted and lettered by our friends in C&W) the winkling out of the correct shape GWR brackets proved a lot more difficult. Over a number of years we had accumulated no fewer than 4 different ones, of which one a pair. Which one (if at all) was the correct pattern?

It turns out that the GWR used castings with a pattern number on it, and the base is pointed on top, flat at the bottom. We did indeed have one of those, but only one. A friendly auctioneer pointed out another pair, and for a fair price we now have a correct set of three. The brackets on the board now need attaching to the wall. The buckets will not be filled with water, as that puts too much weight on our (modern) cavity wall, with just one course of bricks in front.

On its second trip up to Broadway we caught the Ivatt running round in front of the box. We like that BR lined green.


To get it from the front you are talking about a shot into the sun, which is not as good. But here goes, anyway.


In between times Neal was working on fitting the P2 steps handrails. He's drawn a yellow line of masking tape here, to establish where all those brackets need to go.


At the end of the day Neal was a good way to finishing the first run. We still need to rub it down, then varnish it. 

And we got a spontaneous compliment from a pair of visitors on Tuesday about our handrails. People notice quality.




Wednesday with the Usketeers.

Another hot day, but luckily we had the shade of the oak tree.

We made an early start, as it's cool then. We were up to full strength (5 of us) and that meant several points of attack at once.



Jules went indoors (with those thick walls it must be several degrees cooler in there, so a wise choice) and worked on bringing the internal wall up to the trusses. That's how it was, so it will look as if the legs of the truss sort of dive into the top of the wall.




Paul went round the outside and trimmed the ends of the trusses, and attached a number of pieces of damp course (purpose unknown...).






Dave worked on the outside wall facing the signal box - it was hot there. His mortar went off in the sun faster than he could use it.




Jules is a quick worker, and an hour later we can see him on the other end of the internal wall where he started first thing.

 





 

Of course there was regular train traffic - no strikes here - and knowing that visitor 46521 was about we left the site for 10 minutes to catch this interesting locomotive come in from Cheltenham.

Ivatt 46521 enters Winchcombe with the maroon rake from Cheltenham.

Here is the Ivatt at the end of P2, waiting for the crossing train from Toddington.


Paul in one of his usual expansive moods. Probably about fishing in Tewkesbury...

Then we had one of our (many) coffee breaks, and the usual argument about whose cake we will eat first.




After coffee we see Jules stepping back inside (nicely in the shade) to look at how his backing up along the top of the interior wall is looking.

We've go to do something about the chimney area, that is now looking lower than the rest, and the liner is flopping about.





'Pour encourager les autres' we put up some dry blocks under the chimney area. You can see a little row of 5 eight inch high blocks here - now they just need bedding down.




Dave spent his day on the opposite wall to Jules, with the same mission - build the wall up around the wall plate, and up to underneath the trusses. Here he is doing the corner, where the was a hole which once held a stack of loose bricks holding up the end of the wall plate there.




 

 

Outside, Dave did very smart work, building the wall up to the level of the trusses.

Neat, and smooth, isn't it? Now we need to cover all this in Hessian, so that it can go off quietly, and not dry out. With this hot weather that is a clear risk at the moment.



Post scriptum:


Tim Bazeley Memorial Train

As you will have read in an earlier blog, our co-founder Tim Bazeley, one of the originals from the very early days, died suddenly a few weeks back. The funeral was a quiet one for family only, but today his wider circle of family and friends were invited to participate in an early evening train to spread his ashes.

The train ran the full length of the line, starting and finishing at Toddington. It did not stop at any of the intermediate stations.

At CRC we were able to record the headboard made for him specially.


On the way back the train stopped at Hayles Abbey halt, his most recent achievement. Although many people participated in its construction, Tim was instrumental in obtaining support from the board, and the funding.

Now, 5 years later, it is still looking as good as new, and well cared for.


The first two carriages of the train stopped at the halt, and we got out to remember how we all worked together to achieve this.

Members of the same team are now rebuilding the Usk weighbridge, the natural successor to Hayles Abbey halt.

We are open to suggestions for the next project after Usk!



18 comments:

  1. Turntable please

    ReplyDelete
  2. I think platform 2 at Broadway has got to be the next job on the list. It's the most obvious piece of unfinished business on the line as a whole.

    Personally, at some point in the future, I would like to see more done at Cheltenham Race Course. I think it's often overlooked - and I suppose that's understandable, since aside from race day special trains, it's not really a key destination.

    CRC is too far away from Cheltenham itself to really serve the town, and the most interesting part of the station - the original booking office - is hidden away at the top of the cutting, and not even in use any more.

    It's a station most people travel away from, rather than making a point of travelling to. And yet it's a unique asset (no other heritage line has a racecourse station) with its own fascinating history. It's disappointing that nobody has ever shown much interest in that history.

    I would like to see platform 2 brought into use, even if it mostly functions as a vantage point for people to observe the trains. It's odd that the platform was rebuilt at (presumably) a hefty cost, and yet is mostly disused. I've never seen a train at platform 2 - do the race day trains use it?

    I'd like to see a footbridge installed (whatever happened to the extra span from the Henley In Arden bridge? That would possibly do the job) and some platform buildings in the original style, which I think could be built quite cheaply.

    The way the Dean Forest Railway has reproduced the timber buildings of the Severn & Wye Railway in a trompe l'oeil style (the buildings look absolutely authentic, but they're actually concrete block structures in clever disguise) shows how it can be done.

    I would like to see some information boards around the station - as has been done at Toddington - explaining how it all worked. For example, the rail-built crowd barriers near the entrance gates, which were designed to funnel crowds into single-file streams, to make life difficult for ticket dodgers - that's a wonderful piece of history, and the original kit is still in place. Why not draw attention to it?

    ReplyDelete
    Replies
    1. All true, Michael.

      I helped to build that platform, with about 6 others, every Monday for two years. The then chairman (since deceased) was so keen on bringing it to use that at one point he considered bringing in paid contractors to finish it off quickly. The economic case (he must have had one) he didn't explain to us. Something to do with race trains I believe.

      I would like to see a Cotswolds stone replica building at CRC, based on Bishops Cleeve. We don't have one in that style on the railway, and there were two, and we are the Cotswolds line after all.

      I did try to get some historic info from the race course itself, and they referred me to a central racing museum, which said it was closed temporarily. I was after a scan of an original poster, and have since found one on line - check out Broadway in a couple of weeks or so :-)

      An issue is which side at CRC. At the moment passengers have to travel through the race course to reach us.

      The extra span from HIA was scrapped. I think if we wanted a footbridge, we could get one, but it would need restoring. They rust.

      Delete
    2. Just for the record, CRC P2 is used for race trains and at galas, crucially it helps provide a path for the goods train which justifies the investment on its own in my view! :D

      Delete
    3. Platform 2 at Broadway to coincide with the Commissioning of the Signal Box and or the Halts @ Laverton or Gretton please

      I am still in awe and admiration of what has been achieved at Broadway and want to put right all the other historically incorrrect misrebuilds elsewhere but know we cannot have everything

      Delete
    4. Martin Sheppard25 June 2022 at 22:21

      Rather than a halt at Laverton I think one for Stanton would add another walking-distance tourist destination to our railway.
      Also, is a turntable needed when there could eventually be a WSR-style triangle at Honeybourne, and a second one at HuntingButts incorporated into the 'Tim Bazeley mainline link' design?..

      Delete
  3. Naturally, I would say Platform 2 at Broadway. But more urgent might be a carriage shed at Winchcombe.
    Another project might be GWR-ifying CRC, including the repainting of the signal box thre and at Gotherington.
    How about a Broadway type job at Weston under Edge? .......I jest.
    A water tower (Parachute style) at Broadway might be a good one.
    A station at Bishops Cleeve.
    Captain Mainwaring might have said to me at this point "I think you getting into the realms of fantasy there Jones!.
    Whatever it is we will watch from afar avidly.
    Regards, Paul.

    ReplyDelete
  4. A terrific informative blog.thank you.

    ReplyDelete
  5. Appreciating all these projects cant get done without funding and currently that's not the easiest to find, but does the railway actually have a long term wish list, maybe event in some order of urgency.

    You could see the coach shed being in the needed urgently category, whilst something like a turntable in the nice to have section.

    I suppose where I'm coming from, is like some of the loco projects (76077) I'm thinking of specifically; they have done very well out of component sponsorship, and wondered if something similar could be set up for the railways infrastructure, especially with a legacy or a windfall.

    Whilst its not going to appeal to all, some might like to think they have bought a door or the special corner bricks for say Broadway P2 waiting room? Or even a whole building?

    ReplyDelete
    Replies
    1. Yes, a list of potential investments/expenditures was provided at the AGM, so I can pass it on. In no particular order:

      - Bridge repairs, similar to the one just done.
      - Stanway viaduct waterproofing
      - Toddington visitor centre (will it be a railway style building though?)
      - Toddington P1 extension for 8 coaches (like the other stations)
      - Toddington & Winchcombe canopy repairs
      - Winchcombe PWay yard improvements
      - Winchcombe carriage shed
      - Broadway P2 completion.

      The last one on the list should cost the railway nothing - an appeal would almost certainly be successful, and the team is already there to build it.

      PS Guys, try not to post 'Anonymously', select the 'name/URL' option and type in your name. Don't be shy.

      Delete
  6. While not connected with the Signal & Telegraph Department, I believe that they deserve a proper workshop, rather than their existing primitive facilities and that decrepit carriage. A critical department which seems to be treated as Cinderella.
    Puzzled by the emphasis on a visitor centre, particularly at a station which is no longer the primary starting point for our passengers.

    ReplyDelete
  7. Sorry not trying to anonymous, just lack of knowledge!

    Like the list and all needed in the short term. Just wondered on a real wish list?

    ReplyDelete
  8. There are several items on the list provided by Jo that I would think are not wish list items but "must do" items to safeguard the railway e.g. bridge repairs, the viaduct waterproofing,canopy repairs and the carriage shed, others are operationally rational like equal length platforms, canopy repairs and the carriage shed, surely a wish list should be things that enhance the railway both historically and operationally yet probably wouldn't meet the requirements of a capital budget for instance Hayles Abbey and the magnificent reproduction lamp fixtures. It seems to me (as an unbiased observer 4000 plus miles away) that Platform 2 at Broadway is the ideal wish list item as Jo said it has all the aspects there and could be accomplished with minimal cost and provide both historical and operational enhancement. I do agree with Neil that every department deserves a decent work centre.
    Malcolm

    ReplyDelete
  9. Many good ideas here , however more stations and halts will only slow up our trains , complicate our timetable and make the journey too slow for many . More coal would be needed which is the main cost problem for us now . DMU's can fit in with shuttles to stop at Hayles Abbey Halt from Broadway and Winchcombe .

    .My view on CRC is to negotiate a new location at the top of the Coach Park area with access from the A435 out in the open for good GWR exposure and signage .Coaches would still have plenty of space around the Signal Box and the GWSR car park could be parallel with the main road .

    The lovely Heritage Ticket office could be lifted en masse with hydraulics and moved across the bridge to locate at the top of the station , where a pedestrian bridge would convey Gold Cup racegoers over to the grandstands and Platform 1 for return journeys . .
    A Bishops Cleeve station building similar to Broadway on P2 would improve the Heritage feel and vehicle / coach party access via a new roundabout would be best to enable our visitors to leave late afternoon . This should be funded by Highways and Cheltenham council as it would divert traffic away from the congested Prestbury entrance to the Racecourse , and this has always had poor GWR signage for our visitors .

    As Michael says , CRC is our departure station for many visitors to the Cotswolds and from the big towns of Cheltenham and Gloucester, and the M5 from Bristol , all have strong GWR links . The early full trains up from Cheltenham are a delight to witness on Gala days and the Food and Drink Fayre enjoyed welcoming the Cheltenham Spa Express to Toddington !
    Hope this is of interest , john M .




    ReplyDelete
  10. As money is a factor, always, but especially at the moment, it would seem to me sensible to complete the building on platform 2 at Broadway.
    At Cheltenham it is a shame that the one heritage asset, the original ticket hall, is no longer being used for its original purpose.
    Could the disused and partially buried footbridge from near Bloxham Station on the Banbury and Cheltenham Railway be used at Cheltenham?

    ReplyDelete
  11. Martin Sheppard27 June 2022 at 22:20

    I do like the Bloxham footbridge idea!

    ReplyDelete
  12. There is the disused section of footbridge on ruabon station, it is lattice construction. Im sure the guys who made the broadway steel work could complete a new section.

    ReplyDelete