Wednesday, 29 January 2025

Track all back in place.

Saturday at Didbrook.

A good turnout today, as reinstating the track is interesting, and the weather was fine. But what a cold start - frost on the ground, and zero degrees when we arrived at Didbrook 2 bridge.


 

 

This is Didbrook 2 bridge. Our drainage gang was here recently, to dig out the 4 drains, one in each corner. They did a good, neat job here.

That this bridge regularly floods (as does Laverton Bridge) can be seen by the depth gauge on the wall, and by the brown tidemark, which goes up to 5 feet !



 

Our mess coach is stabled just above, so we climbed up to the trackbed and deposited the day's goodies on the table:

Seven chocolate croissants, and they didn't last long. We have discovered a source of these in a nearby mini mart.


 

 

 

The first job was to use the digger to tweak the newly clipped up 4 lengths into a better line. This really helps the tamper, which can only shift a few inches at a time.

 

 

 

 

 

 

 

 

At the end of the tweaked 4 lengths we can see that the rest of the track has now been laid, but that a lot of cutting, shutting and clipping up remains to do.

We cut off about a foot from each end of each rail. This is for welding (every other length) and to take off the dipped ends for a smoother ride, and fewer cracked fishplates. 

The accumulated feet soon mount up, so each next rail needs to be dragged further. As we are on a curve here, pulling at it didn't work, so we had to lift each rail out of the chairs, move it along, and then wriggle it back into the chairs. That was quite work intensive.

 

Looking the other way, from about the same point. Both cutting and clipping up can be seen.

 

Nick had a go on the hired in electric rail saw. We are still trialling this, over several days.

Behind him, next to the pole, is Stanway house fountain. It's a single jet, 300 feet high, and the highest gravity fountain in the world. It's fed by a reservoir on the hill behind it.

This reservoir was the power source for the unusual hydraulicly powered locomotive on the short lived Didbrook branch. Locals talk of a Parsons turbine on the tender of the locomotive, a large reel and a hosepipe back to nearby Stanway house.

The unusual technology was apparently not developed further, as while it was running Stanway house could not run a bath, to the dismay of His Lordship. The final blow was cartwheels coming down Stow Hill, which would repeatedly damage the hosepipe across the road. In the 1960s the Western region had diesel hydraulics, but way before that Didbrook was first in trialling the water hydraulic. Country craft, eh?

Not many people know that.

Watching Nick from a safe distance (Paul Fuller)
 

 

 

 

As every other panel had fishplates, new holes had to be cut into each pair. 

Here David and Tim prepare the drill. This one is a four stroke, and never gives us any trouble. But, unlike the disk cutters and impact wrenches, its operation is quite vibration free.




 

 

 

Here the rail drill is being operated by David.

Swarf in the foreground shows where holes have recently been cut, and a stiff, deep skirted fishplate fitted. 

That won't give us any trouble for a long time.

Note also the Panlock keys, which don't fall out. Although the one on the right might - it's not fully home.

Pete and Tim bolt on a fishplate. Older style Mills keys in the foreground.








(Paul Fuller)






(Paul Fuller)

 

 

 

 

Having moved each rail forward to close the gaps again, many rails wanted to twist as they were on a curve. That makes it hard to get the keys in. The team on the right was well away, while Tony on the left is struggling, as Yours Truly with a turning bar tries to persuade the rail back into an upright position. 

Bullhead rail is very flexible; FB less so.



 

 

 

 

The next section is finally fully keyed up!

Kevin gives it a nudge with the 360, while Bert Ferrule tells him which way to go (or maybe he's listening to Saturday Night Fever).

 

At the end of the day we had cut and keyed up six more sections. That takes us to the 10th of the 17, plus an extra one for all the bits we cut off. That is in store on the ELK in the distance.

We were very happy with progress at the end of the day.

The appeal for some donations for the PWay tool fund (last week) was honoured by a number of people, to our great joy. Thank you for your support, we will spend it wisely.



Back to Broadway.

High winds - some storm name or other - but sunny, with a very wet underground on Monday. A digging day at Broadway! The digger is on hire, so we need to get on with it.




 

This is the starting situation, the circulating area at the bottom of the stairs, with a high bank behind it. There is a pile of clay on it which Neal put there to back fill the hole on the right once the concrete is in, but we no longer need the fill now.




 

 

First Neal built himself a little ramp, so that he could track up on to the bank.




After that we could start digging, and soon the first dumper load was emptied into one of the trucks.



 

 

Alas, the thick clay began to stick to the bucket, and eventually it stayed in there, even after repeated shaking.

Digging it out was no sincecure, it was tough stuff, and gluey.



Once up on the bank Neal was able to track along it and start to reduce its height. The spoil from that was dropped on the ramp behind the digger.

Yours Truly kept an eagle eye on what came out. The surface layer behind the old building is full of demolition rubble, including glass and china.

For example: this broken inkwell. Recognise the letters? We found two more, intact, last summer. Sadly this one is a bit too far gone.

More interesting was the next find, a Codd bottle, with the top snapped off  (quite a common phenomenon, in the day people would break the top off to get at the little marble inside)



The Codd bottle, probably filled with mineral water, or perhaps ginger beer, was marked W. E. Smith, Redditch, Trade Mark.

We showed this to Paul, who has an interest in the history of Redditch, and the Redditch - Evesham railway line. He immediately messaged back with the picture on the right, his latest acquisition: a 1906 season ticket in the same name! It looks as if the proprietor lived in Stratford on Avon, and commuted to his factory with this monthly season ticket, third class. Change at Broom! Monthly cost: £1 4s 0d.

Based on this, we would say that the bottle was dropped into the clay behind the old waiting room round about the time of construction of Broadway station, i.e. 1904.

Back to digging and dumping.

We now have two conduit risers in the platform, and care had to be taken not to damage the plastic liners with the dumper passing over them. From the picture you can see that the track of the dumper is barely wider than the width of the top of the conduit, so after a while and some near misses we decided to dig in some reinforcements, and finally a large plywood sheet over the top.

After lunch there was a further brief spell of windy sunshine, with a few showers forecast later on. How right that was, except that the Met Office failed to mention just how heavy they would be. 

The sky went black, and we fled to the safety of the P1 canopy.



 

The signal box in the background is misty because of the heavy rain falling down. At least we were dry.







After 30 minutes the sun appeared again from the south, making a rather pretty picture.


We turned round to face the other way, and it was even prettier !




At the end of the afternoon Neal had scraped off the top of the bank behind the building.




This area outside the south end had a pile of debris on it, and that was also cleared.

Finally Neal built his little ramp again, so that he could get down.

It became clear that we would easily fill the two wagons again, with possibly more in the future, although there is unlikely to be time this winter. More fill needs to go from beneath where the photographer is standing, as well as from under the digger where it is in the picture.




Tuesday - more digging at Broadway.

The forecast was for light rain all day, so we thought we'd give it a go. In fact it was heavy rain first thing, then showers, and we managed to dodge these, so didn't really get wet. Amazing.

 We got a lot done on Tuesday.

 

 

 

 

Here is Neal round the back, where he set out a line for the path around the building to be laid out. This will be paved and measure 900mm wide.

As the terrain on the left rises, in line with the field, the terrain will at some point be supported by a low wall, which will end up by the footbridge tower that you can just see in the picture.





We are now digging into pure clay - no more 120 year old finds - and this became a big problem for us, as it kept sticking to the digger's bucket, as well as to the inside of the dumper. Vigorous shaking didn't help, and prising out with a shovel was nigh impossible. So we cleaned the bucket thoroughly once, and then dipped it in the water filled hole each time to lubricate it, a bit like they do in ice cream shops (if you frequent these).


We spent the whole day digging, with no distractions. The heavens threatened, but just a handfull of showers came down. The wagons were almost completely filled by the end of the day.

 



The dumper can tip only so far into the wagon, so once they were completely full at the front Neal came and pushed everything back, to create more space.

This should give us another  10 - 12 dumps for when we come back on Thursday.


This was the result at the end of Tuesday. Look how everything glistens - the clay is soaking wet. The little pond in the foreground is for the foundation block for the third canopy support column.

The ground between the back of the building was taken down by about a foot, and sloped downwards. The path around the building has been dug out, and a trench created to take some concrete for the base of a wall.

The ground where the photographer is standing also needs to be dug out, and a big tree stump removed. So it looks like at least another two wagon loads are required.



Wednesday with an Usketeer.

Dave is still away with minor ailments, and he is much missed. Just Paul and Yours Truly today then, but we still did well.



Before we start, a brief word about the Greet Road overbridge. This is not owned by the railway. It was resurfaced last year, then a hole was cut into the tarmac. That has turned into a sizeable pothole, and now a weight limit of 7.5 tons has been put on it.

That could be awkward for our wartime childrens' experiences, as they come by coach and one of those weighs, typically, 13 tons.


In the weighbridge hut we started to take up the floor. It was damp all over, with a particularly large patch inside the door.


 

The Winchcombe weighbridge was rebuilt after the war, and we are discovering what that meant in practice. The ground outside it, strangely as with the weighbridge hut at Usk, is much higher than when it was new. The floor inside is niow sunken, compared to the outside. Outside the door a patch of concrete slopes downwards towards the door, and in the recent storm this is where water ran into the building. We need to address this.



We took up the bricks in the floor, and found a layer of ash underneath, and a further hard layer underneath that. What could it be?

The ash was damp, and seems to act as blotting paper to damp coming in from underneath, and the sides.






We took up all the bricks in the floor, leaving an irregular patch of concrete. This was very ugly. We decided to give it a neat, straight edge, and ran a cut along the side of the balance mechanism.




The dust that came out of that cut was extraordinary. It poured out of the door for a good 20 minutes, which we passed sitting a good distance away. It even came out of the chimney.












Ad interim, a quick picture of the C&M team getting the Winchcombe footbridge ready for new, non slip covers for the treads.

The area was thouroughly cleaned with a pressure washer, which also took off a lot of the paint previously applied. This will be repainted.


Outside, measurements were being taken for the new woodwork for the refurbishment of the entrance canopy, and its two new bracket castings. This project is now getting new impetus.





Inside the weighbridge, sweeping the ash that was underneath the bricks in the floor revealed - a second floor, also of bricks. Surprise !

So the floor has already been raised once.

We will remove the ash next time, and put down a damp proof membrane on a bed of sand, itself also covered by a bed of sand.





PWay at Didbrook.

The track is all back in place now, the gang having reached the southern end of the relay site. Rail has been lifted in, cut, and clipped up.

Paul, our PWay manager was very busy on site today, but he did manage a couple of drone pictures for you.

The current site stretches from the foreground, up to the mess coach centre top. The first relay (of the same economy sleepers) two years ago went from the mess coach to the smokey area at the top, a similar length.

With this second relay all wartime economy sleepers have been removed. They are now in store, and will be used again in various sidings, for which they are still suitable.

The Hayles end of the relay.

Closure rails still to go in.

Lastly, a drone view of the Hayles end, looking south.

Paul was very happy indeed at the end of the day. We are under some pressure to get everything serviceable again asap, as there are race trains on the horizon.

Lining, lifting and packing the track are next.

Note that the B4632 is closed until April 4th, between the Toddington Roundabout and the road to Stanton. It was resurfaced last year - are they cutting it open again?

 

 

15 comments:

  1. Good work at Broadway. For the onlooker, it is as though you had started the Boadway canal company at one stage! For a two man team, you have achieved miracles there.
    The ink well, abeit broken, and the bottle were interesting finds.
    Also to be congratulated is the re- laying team at Didbrook. Gone, it seems, are the wonderful cooking aromas from the mess coach from when you were working to get tracks to Broadway.
    I raised the question of staffing Broadway signalbox, and got an answer, which is, that the box will be staffed some time in 2025! that seems a wonderful thing to happen to look forwards to. the sound of train telegragh bells at last! Result.
    Regards, Paul.

    ReplyDelete
    Replies
    1. We heard a rumour, but there was nothing for Broadway on the roster for March. maybe later?

      Delete
  2. Corrections & Clarifications. The rail drill is a two-stroke, not a four-stroke. But as pointed out it's a reliable performer, unlike it's impact wrench and rail saw brethren.

    ReplyDelete
  3. Strange one, before I settle down to read this properly.
    This blog is no longer in the GWSR blog listings. I had to Go Ogle Search for it today.

    Has it stopped being affiliated, or has a finger slipped by mistake?

    ReplyDelete
    Replies
    1. Others have reported this as well, and I checked - it's true. I have no idea why.
      I shall make enquiries.
      I suggest you bookmark the blog link, rather than go to the plc website.

      Delete
    2. Glad it's not just me getting it wrong then.
      Bookmarked page , yes.

      Delete
    3. It could be an expensive oversight. The work at Broadway and around other parts of the railway is inspiring and attracts funding to the railway. Publicising the blogs should be a priority for the marketing people.

      Delete
    4. We actually have a new marketing manager - the well known Jack Boskett!

      And yes, the blog does motivate people to help financially, there is plenty of evidence for that.

      Delete
  4. I have used this link
    https://acahl.org.uk/GWSRblogs.html
    ever since the amateurish PLC blog upgrade that no longer shows recent blog posts or updates. Keeps me up to date.

    ReplyDelete
    Replies
    1. That's really interesting - you can see which ones are really active, and which are moribund (usually because no one wants the work of writing them)

      Delete
    2. A good link, Thank You. It also has the bonus of a link to the "Restoration and Archiving Trust" which isn't on the Blogs page.

      Delete
  5. The blog link was created by a GWSR member at the time of the PLC blog update, which was changed to include a " health warning" disowning blog writers and didnt link to updates as previously. A strange attitude to take to such a well loved and supportive body of bloggers who do nothing but good. What were they afraid of? Hopefully the new Marketing guy can appreciate and encourage bloggers and take down the health warning.

    ReplyDelete
    Replies
    1. It doesn't disown us blog writers, it merely makes it clear we are unofficial publications, which protects the writers just as much as it protects the railway - it was something I made sure was added when the new website was developed and I did a proof-read. "GWSR Plc wishes to support those of its members who write blogs describing the work of their respective departments". The rest is perhaps a little clumsily worded, but there has long been a caveat of some sort. It's a shame that it didn't automatically link to individual posts as it did before, unfortunately technology defeated people on that occasion. The price we paid for progress on that occasion unfortunately. Happily viewing numbers have held up despite that, certainly on the C & W blog, and some clever clogs came up with an alternative to keep the automatic post updates accessible too, so everyone ought to be happy - at least once the link gets reinstated. Very odd, but easily resolvable no doubt.

      Delete
  6. Thankfully l found it ,was a bit worried that something bad had happened. Can't do with all this covering your backside rubbish unfortunately there are some pedants who will take offence of just about anything these days. Ove the blog though and am amazed at what you all achieve.

    ReplyDelete
  7. Hurrah it's back on line ! I called in for a splendid run up and down on a beautiful January 2nd day and was very fortunate to be shown around the new steelwork at Toddington by Neil, what a gent !

    ReplyDelete