Friday at Broadway.
'Bert' has passed, and so has the overnight frost, so we are back on brick laying.
During a visit to the signal box, we were surprised by this large helicopter.
It approached Broadway from the west, then circled it once, before flying off over the Cotswolds Edge.
A man in the open door on the side was looking down on us.
Down below, you can see that the empty wagons have been returned. We now need to arrange for the digger to be re-hired.
While John was laying bricks along the back of the building, we cleaned the remaining blues found in the previous excavations, and added them to the two pallets a bit further up north.
We also reduced to small pieces of rubble another wheelbarrow load of broken bricks and concrete. This was tipped further along as well, where the platform as currently is has dropped a little as the infill consolidates.
The main job for the brickie's support, next to making up mixes of mortar, is to cut bricks in half. This is to enable him to simulate English bond with short headers (which are in reality cut in half, and thus much shorter).
The work is very dusty. Everything goes pink. We create about 100 of these half bricks per brick laying day, and thus keep ahead of John (who is also laying strechers)
This brick laying, and indeed cutting, is gradually making an impact on our stocks.
Here you can see two empty pallets, and a third nearly so. Behind is an original shrink wrapped pallet.
The three pallets in the foreground had randomly stacked bricks, which had been prepared for use in 2017, but were never used. Many are slightly chipped, due to the repeated manipulation of the slightly fragile bricks. Part of our job is to sort these out, and cut off any damaged ends and so turn them into (half sized) headers.
At the end of the day John had completed the fourth course along the back, and also along the northern gable end.
A fifth course was started at the back. John is wary of doing anything along the front, as Neal could come through there at any time in the hired in digger.
Saturday, out with the gang.
Ten of us on Saturday, a good turnout. Last Saturday was only 5, plus Bert, the storm.
Saturday's mission was concrete sleeper replacement, so here we are loading a couple of spares.
Two are already out there.
The jobs were at Broadway. Here we are by the lovely, but currently useless bracket signal.
We had the mini digger with us, but it took so long to change the buckets from wide to narrow that the gang got bored, and dug the first one out by hand. The ballast here was brand new and not too big, so digging into it was easier than usual.A cracked sleeper. |
We got the two sleepers in question out, and to one side. With two exceptions, the gang here asked to replace them is the same one that put them in there in 2017.
That'll teach us!
Just ahead is Broadway station, and the draw was the PWay train, with mess coach, in the platform by Christmas. We did it too.
Below on the right is the council owned Broadway station car park. Although there were no trains, it was heaving, and full right down to the bottom.
Mrs. Blogger, on a mission to scour Broadway for Christmas presents, was one of the 'Parkees' and reported seeing us up above.
We however were busy shoveling, to back up Lee on the Robel.
We had a whole fleet of vehicles with us as well - Andy's van, the Transit with the tools and spare sleepers, the Ranger and Trailer for the mini digger, and finally David in the Telehandler for the muscle.
Then we moved down 3/4 mile to the next pair that needed replacing. This was by the fixed distant.
Only just after lunch now, and the skies were darkening already.
This time Dave was ready and with the right bucket, so the exchange of sleepers went swiftly.
The mini digger certainly helps a lot, we were very grateful.
Putting the ballast back is still done by hand, then we Robel pack the scene.
This was the fourth sleeper that we replaced. It has a large chip missing. It's not a severe fault, but since it was marked up and we had all the kit on site we took it out.
All four replaced sleepers were lifted on to the new white Transit, to be taken back to Winchcombe. They are still good for a siding replacement.
We were quite impressed with the new Transit's performance under load. The engine still had quite a bit of pull, and the handling was fine. A Citroen tipper we had (since sold) was gutless, and tended to wallow under load. So this one is a big improvement.
Monday, back on bricks.
We pick our working days depending on the weather (and personal availability). Monday was good for both, so we were off again.
John worked along the back again. Half in this picture is up to the fifth course.
At the end of the day he had completed the fifth course along the back. It was a shorter day, not only because of the daylight, but also as rain was forecast for the afternoon.
So we stuck to two mixes, which basically completed the back on the fifth course. All in fiddly little half bricks.
Neal came after lunch...
The front is ready for some window cills on the third course, so Neal had a happy hours setting these out, and trying out various combinations of bricks around them.
In response to a blog question, the cills we had were dirty after 10 or so years in store, outside. Neal did a good job on them with a pressure washer.
We were also two cills short, and these have been ordered.
The new door frames are expected around Christmas. It's all moving along.
Wednesday with the Usketeers.
We are back ! And we have a new project - The repair of the Winchcombe weighbridge hut, one of the few original buildings from 1905.
Here it is on the left. The weighing mechanism is intact, and fully functional.
In the very early GWSR days the railway sold off unused land at Winchcombe, and this allowed two houses to be built adjacent to the station approach. The neighbour here - newly arrived, and already a volunteer on the railway - has inherited a garden that is so close to the weighbridge hut that there is less than a foot all the way round it. And the inside of the weighbridge hut is very damp. That is the situation that we have today.
The gate into the yard is a modern farmer's gate, and there is a (currently unfunded) idea to convert this to a wooden GWR style 5 bar gate. The original gate posts (that led into the goods yard) are still in situ. A GWR lamp post would also be in the right place on the island.
The FoWS were mystified by a persistent leak from the gutter in the middle of the front.
Closer investigation by the Usketeers revealed that this was caused by one of the gutters sinking, due to a long crack that went round the arched window, and right down to the bottom
The cause of the crack looked to be a stone lintel that crossed the weighbridge beam pit. The lintel was cracked.
The Usketeers made a proposal to rectify the cracked lintel, and rebuilt the front wall, back up to the top.
This was accepted, and today was our first day on site.
We decided that a joint approach to the subsidence with our nearby friends from the Construction and Maintenance dept. would yield the greatest amount of brain power, for what would prove to be a rather complex problem.
Here is C&M Martin examining the failed stone lintel.
This turned out not to be stone at all, but a pair of thin RSJs in very poor condition, boxed in by weak concrete and chicken wire.
We eventually worked out that the weighbridge must have been renewed at the end of the war (contemporaneous with a rather ugly 1940s toilet block that was found on site when we took over in 1981) and the new mechanism, taking up to 20 tonnes, was much bigger, and installed a few inches higher than the 1905 original.
Over time the ground level around the hut had also been raised, so that the hut was no longer proud of the ground level, but actually set below it. This also contributed to the damp inside it.
Close examination of the crack also showed that the main reason for it was subsidence of the corner here, possibly exacerbated by water in the downpipe (removed, next to the spade) which possibly led to just a nearby soakaway.
The team from C&M soon got to work digging out the corner, to see where the water actually went to.
It was agreed that the Usketeers would start on the failed lintel, by building two supporting towers underneath it.
Larger digging means were brought in, as the failing corner became more apparent, with 3 courses of spalled bricks at, or just below, ground level.
It was decided to underpin the failing corner, for which we had to get back to the original foundations.
The Usketeers expressed concern at the debris in the very narrow passage around the back of the hut as well. This clearly had not been addressed, perhaps since the plot was sold 45 years ago.
To get at it, we had to remove the end of this hedge, which had a failed picket fence inside it.
To our astonishment the tiny space left between our building and her garden was half filled with soil, a left over from the previous owner, who grew vegetables here. This easily explained the dampness along the rear wall in the hut.
The FoWS were keen to remove the soil and debris asap, and will do so later this week. We have the full and very kind collaboration of the neighbour, which is a relief.
When we return next week there will therefore be two work sites here then, and two teams working, helping each other.
It was a most useful start to a tricky problem. But we must look after our original heritage buildings.
PWay update.
A rather frustrating start to the day on Wednesday. Not only did the Ranger have a flat tire, but the replacement vehicle intended, the white Transit, turned out to have an incompatible socket at the rear, which meant that it could not pull our trailer to the intended work site.
A timber was replaced on the Winchcombe south points, but we could have done so much more. Just bad luck, but we will prevail, it was only time that was lost.
One project that was able to be advanced was the fitting of several small new rubber matted crossing points alomng the line. This is to enable our contractor's flail mower to pass from one side of the track to the other.
This one here was installed in the Dixton cutting, near Prescott. More will be fitted.
A clear out of the S&T yard also unearthed a quantity of original insulators, mostly marked BR (W).
We have put them up for sale as you can see (in the Cotswolds Halt), togeether with a sample rail end, for door stoppers or mini anvils, or any length that you might desire.
The Broadway digger is coming back on site on Thursday, to fill the two wagons again. This time we will be excavating the pit for the foundations at the foot of the footbridge steps.
In the early days I got hold of some wooden planks and along with Kevin Markham we secured the weighbridge and goods shed. This worked well until someone broke into the goods shed and started a fire. I was in Birmingham when the fire brigade called as I was the key holder and they wanted access needless to say I agreed that they could cut the lock and fortunately they saved the building although some of the decking inside didn't look too good. Nice to see that the weighbridge is to get some much needed TLC.
ReplyDeleteRegarding the white Transit. By "incompatible socket" do you mean the towing electrics ? A 13 pin socket on side and a 7 pin plug on the other, or vice versa ? No need to re-wire everything. Adaptors are available to allow the two to connect. I'll take a look this Saturday.
ReplyDeleteThe reason it takes so long to swap buckets on the mini-digger is because it's old school and is not equipped with a quick hitch. Everything directly attaches to the dipper arm and tipping link and there's quite a bit of faff involved in knocking pins out, getting everything all lined up, and then knocking pins back in again.
Really moving along now at Broadway with window lintels going in. It's a very big pat on the back for yourself as the provider of the cut bricks that John lays in place. When you mentioned the brick dust in a previous blog, the thought came to me (remembered from what an old and probably now deceased ex GWR worker said) that the GWR would not have wasted the brick dust then. Because before Brasso was available, brass and copper were shone up with a brick dust and parafin mixture. Very abrasive to the brass and copper but it did the job at that time where brass replacement was quick, cheap and easy from the stores at Swindon or Reading rspectively, if the brass or copper item wore out. I did actually try it on a very gunge clad item or copper that I wanted shone up, and it worked very well. This was of course a one off thing as I wanted the copper to last longer than it would have if I continued with brick dust and parafin!!
ReplyDeleteRegards, Paul.
I wonder if John is placing wall-ties occasionally in the brick courses to tie in with the concrete block inner leaf when it is eventually built? Is the intention to go to full height with the brick outer leaf, then build the concrete blocks up, or will those go in earlier, perhaps at the time when scaffolding starts to be needed (chest height?)?
ReplyDeleteYes, John is placing wall ties.
DeleteThe rest is not yet decided, it's up to a whim...
Joe,
ReplyDeleteI enjoy reading your blog very much, but I am a little confused about the difference between the Usketeers and the folks working on Broadway platform 2. I was looking back at your archive and it seemed that the work on Broadway was given to "you", meaning your group.
This request for clarification is not meant as a criticism. I think you all do a fabulous job and railway is better for all you do. Thank you from a supporter and member of the GWRT.
It's two different gangs, and I work with both of them. I also work on the PWay. Many people on the railway have more than one activity.
DeleteJo, Sorry for spelling your name wrong in the previous post.
ReplyDeleteOnly 4 duff sleeper out of hundreds we laid down after inspection at skew bridge compound is pretty good. , they were special days laying track in 2017 !
ReplyDeleteSee you all again on Tuesday for the Xmas lunch , yum yum ! Merry Christmas Daily M