Friday, round and about.
A small team of 4. David set off in the Telehandler for Didbrook, to help contractor Kevin add some of the better ballast to the newly relaid track, to enable further levelling.
Paul, Nigel and Yours Truly tackled what was thought to be a 'quickie', but which took rather longer: lower the two troughs opposite Winchcombe SB, so that the lids don't touch the rails.
You may recall a recently resleepered panel here, when the troughs were already noted as being too high.
As the cables inside them were thick and stiff, moving the troughs was rather difficult. After some head scratching we appealed to nearby FoWS for some gardening hand tools, and armed with a little rake and a trowel, we scraped ballast and compacted ash from under each trough.
Once one trough could be rotated out of its bed, the latter could be scraped out, and an adjacent trough pulled into the lower position. The process was then reversed.
In this way we achieved the asked for 1 inch headroom under the rails. It took us all morning.
During a trip to Toddington we came across the Broadway spoil train, which was just arriving in the yard.Then it was on to Didbrook to deliver supplies, and check out how Kevin and David were doing.
![]() |
Paul and contractor Kevin discuss progress. |
A lot of the ballast removed here is still good for bottom ballast, so we have been putting it back, prior to adding expensive new ballast to the top.
![]() |
Picture by David. |
Here's a (bit of a slanted) view of the situation at the end of Friday.
The relay is looking pretty straight and level now, although it needs more packing at the southern end.
Next will be a ballast drop, followed by tamping.
Looking back a few years, to the same place:
A wagon loaded with track panels, recently lifted from Quedgley, has been pushed to the end of the line. The first shuttle services from Toddington were terminating at Didbrook, just out of sight.![]() |
Pictures by John Lees, of the PWay gang |
The panels were lifted off the wagon by a crawler crane, and laid directly.
Those with sharp eyes will see that these panels are fitted with the wartime economy sleepers, which we have now all replaced, over two seasons.
The date is 18.08.1984.
Just a general enquiry now, out of interest.
We use a Lister generator on the PWay, and we wondered if anyone could say any more about it?
We have had it for a long time, possibly since the start (1980s). It still works fine. Just use the two decompression levers (on top) and crank the axle (centre right) and off it goes. It's a two cylinder diesel model.
This is the works plate. There is no date of manufacture.
Can that be determined from the number?
Monday, a ballast train at Didbrook.
Now that the track is back in place and roughly aligned we are able to add fresh ballast, ready for tamping.
Three of us dropped the first load of ballast at Didbrook on Monday.
First, we shunted the mess coach and vans back to Toddington, then went to pick up the ballast train from the Parlour Road.
The DOGFISH were expertly loaded, another compliment for our contractor Kevin. You couldn't get another stone in. And it was his first time too!
Here we are, coupling up to the wagons. Would they hold the vacuum?
Hmmmm... mostly. There's a leak on a hose somewhere.
There's a video of it here:
And this was the result. Doesn't it look good? Almost ready to run on. But first the tamper has to do its job. That's coming later in the week.
After the drop we reversed back to Toddington, giving this view from above. It was bitterly cold, despite the sun. The crew of the shunter taking the clay wagons back from Broadway already mentioned how cold it was as they went along, and now we could feel for ourselves why they said that.
Passing through the Toddington North cutting, we saw the results of the slip stabilisation works done there last year. Drainage was clearly important.
Further along we approached Stanway viaduct.
This all looks very neat and professional, with the waterproofing done, track reinstated and parapets stabilised.
A close up shows how the parapets were stabilised, with stainless steel guy ropes attached to wall brackets. These offer the opportunity for individual memorial plaques, and the blue squares show the ones that have been taken up. This raises funds for the viaduct repairs that are still due, to rectify the damage done to the brickworks by the water that used to leak through. That's going to be a much larger bill.
If you want to help with a plaque, here is the link:
https://www.gwsr.com/support-us/stanway-viaduct-commemorative-plaques
Wednesday with the Usketeers.
Another bitterly cold day today, exacerbated by a nasty wind and a sneaky mizzle, which made you wet without you noticing it.
The first job of the day was before we even got to work - it was to open up the gates to the yard at Stanton. More ballast was arriving, in 30 tonne loads. Big stuff.
Then it was on to the Usketeers at Winchcombe, who also had arrivals, but of a more modest scale.
Here is Dave, with a barrow of sand for the new floor.We had a planning session first thing, to decide on the floor level we wanted to agree on. The DPM will wrap round the new floor, and up the sides beyond it.
It struck us that the inside of the weighbridge hut was already less damp than last week, as evidenced by far less moisture on the windows inside. On the other hand, the underside of the DPM, when turned up, was soaking wet. So the damp is definitely rising up from the old floor, provoked by the higher ground now outside the building.
Here is what the first barrow loads of sand looked like in the corner.
The bricks for the floor are stacked outside. On further examination they are all surrounded by very hard mortar, probably poured into the cracks when this (second) floor was laid. It has to come off though, before we use the bricks again.
Lunch was taken inside the weighbridge hut, with the mizzle continuing outside.
The Usketeers were delighted when lunchtime was announced...
After lunch we started on relaying the actual floor. You can see how it fits inside the protective Damp Proof Membrane.
We forgot the end of the day shot, but it was a bit further than this. Paul was laying the bricks as fast as we could clean them, and at the close of play on Wednesday we were about a third of the way there.
A little bit of news on the Winchcombe entrance canopy - two members of C&M were taking down some of the end of canopy woodwork, so that it could be extended.
Before re-erecting the canopy brackets, we are waiting for the fixing holes to be drilled into the new castings.
Also at Winchcombe, something negatively affecting our aim to be a 'living railway museum'.
Sadly, it's another example of operational needs/wishes pushing aside our desire to be the 'Best heritage railway in the country' ( a director quote from a shareholder meeting). The undisguised plastic meter and junction boxes have now been joined by a gas store and new electrical terminals in the middle of the lawn, which itself has been part urbanised with concrete paving and pub type picnic tables.
We are not singing from the same hymn sheet.
More work between Didbrook 2 and Hayles Abbey Halt.
The welders completed the welding of every other rail joint
Here they are grinding down the excess weld material, and giving us a perfectly smooth ride, with no jolting dipped joints.
Every other joint will still be fishplated, but with cropped ends, also to give a ride without bumps (and cracked fishplates).
On Wednesday the gang freed off the ends of the sleepers, after Monday's ballast drop.
This is necessary, so that the tamper operator can see the sleepers he is supposed to lift.
And the tamper has arrived! It's an old friend, Bob and Rick do all of our tamping on this venerable machine.
In the picture is a PWay briefing about the job.
Also, during Wednesday a tractor-trailer was hired in to remove the spent ballast.
Here it is removing one of the piles. The spent ballast was taken to Winchcombe. We have several ideas for what to do with it.
We also still need to remove the piled up 'wartime economy' sleepers.
These will be stored at Toddington, but not for long, as we have plans to re-sleeper 'siding 2', and they are ideal for that.
Finally the 'cube' was taken off site and to Toddington.
The trackbed is ready for Bob and Rick, with their tamper.
We have one more job to do for the welder, and that is to weld in an insulated joint at Gotherington Skew, in place of a fishplated insulated joint, which was giving us trouble on that curve there.
That is for next week.